Below is a listing of the Revisions and Changes made to UFGS Sections for each release. You can narrow the list by selecting a UFGS Release date from the drop-down and clicking 'Apply'.
| KEY | PREPARING ACTIVITY (PA) | A Army | N Navy | F Air Force | S NASA [ARCHIVED] |
|---|---|---|---|---|---|
| ACTION | N New | R Revision | C Change | D Deletion |
| Release | PA | UFGS Section | Date | Action | Change # | Nature of Change or Revision |
|---|---|---|---|---|---|---|
| Aug-2022 | A | UFGS 35 01 41.00 10 Electromechanical Operating Machinery for Locks and Dams | Aug-2020 | C | 2 | Incorporated various CCRs. |
| Aug-2022 | A | UFGS 35 20 14 Stoplogs | Aug-2022 | R | Complete review and update. | |
| Aug-2022 | A | UFGS 35 20 16.33 Hydraulic Miter Gates | Aug-2022 | R | Complete review and update including section title change from MITER GATES to HYDRAULIC MITER GATES. | |
| Aug-2022 | A | UFGS 35 20 16.39 Hydraulic Sector Gates | Aug-2022 | R | Complete review and update including section title change from SECTOR GATES to HYDRAULIC SECTOR GATES. | |
| Aug-2022 | A | UFGS 35 20 16.46 Hydraulic Tainter Gates and Anchorages | Aug-2022 | R | Complete review and update including section title change from TAINTER GATES AND ANCHORAGES to HYDRAULIC TAINTER GATES AND ANCHORAGES. | |
| Aug-2022 | A | UFGS 35 20 16.53 Hydraulic Vertical Lift Gates | Aug-2022 | R | Complete review and update including section title change from VERTICAL LIFT GATES to HYDRAULIC VERTICAL LIFT GATES. | |
| Aug-2022 | A | UFGS 35 20 16.59 Closure Gates | Aug-2022 | R | Complete review and update including section title change from CLOSURE GATES to HYDRAULIC CLOSURE GATES. | |
| Aug-2022 | A | UFGS 35 45 01 Vertical Pumps, Axial-Flow and Mixed-Flow Impeller-Type | Feb-2021 | C | 1 | Incorporated various CCRs. |
| Aug-2022 | N | UFGS 46 07 53 Packaged Wastewater Treatment Equipment | Aug-2022 | C | 1 | In response to CCR 11920, NASA tailoring was added to the Electrical Work paragraph (3.2.2) |
| May-2022 | N | INACTIVE-UFGS 09 97 13.15 Low VOC Polysulfide Interior Coating of Welded Steel Petroleum Fuel Tanks | May-2022 | R | Complete review and update. | |
| May-2022 | N | UFGS 01 30 00 Administrative Requirements | Nov-2020 | C | 2 | Per CCR 9893, updated the Note in paragraph COLOR BOARDS FOR AIR FORCE PROJECTS (1.3) tailored for AIR FORCE to include AFI citation. |
| May-2022 | A | UFGS 01 31 20 Project Technical Data Management and Visualization | May-2022 | N | New UFGS | |
| May-2022 | N | UFGS 01 58 00 Project Identification | Aug-2019 | C | 4 | Per CCR 11078, updated Construction Project Signs paragraph (1.4.3) tailored for ARMY and AIR FORCE to address project identification signs for Air Force projects managed by USACE. |
| May-2022 | A | UFGS 01 91 00.15 10 Total Building Commissioning | May-2019 | C | 3 | Updated qualifications for electrical technical commissioning specialist in response to CCRs 9054, 9096, 9741, 9970, 10182, and 10471. Updated burn-in duration for lamps in response to CCR 9218. Updated paragraph "Design Review" in response to CCRs 9220, 9222, and 9237. Updated and changed paragraph "Acceptance" to "Equipment and Systems Deficiencies Check" in response to CCR 9223. |
| May-2022 | N | UFGS 02 85 00 Mold Remediation | Nov-2018 | C | 1 | Per CCR 11701, removed reference to UFGS 00 22 13.00 20 in first Editor’s Note of Description of Work paragraph (1.3.1) |
| May-2022 | N | UFGS 05 05 20 Post-Installed Concrete and Masonry Anchors | Feb-2021 | D | UFGS-05 05 20.00 27 superseded by UFGS 05 05 20 without Revision. | |
| May-2022 | N | UFGS 05 05 20 Post-Installed Concrete and Masonry Anchors | May-2022 | N | Unified / Section Number Change: Superseding 05 05 20.00 27 without Revision | |
| May-2022 | N | UFGS 05 05 20.00 27 Post-Installed Concrete and Masonry Anchors | Feb-2021 | D | Section Number Change: Superseded by UFGS-05 05 20 without Revision. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| May-2022 | N | UFGS 09 97 13.17 Three Coat Epoxy Interior Coating of Welded Steel Petroleum Fuel Tanks | May-2022 | R | Complete review and update. | |
| May-2022 | N | UFGS 09 97 13.27 High Performance Coating for Steel Structures | May-2022 | R | 08/25/2022: this version has been made inactive and replaced with the previous Feb 2021 version. Complete review and update. |
|
| May-2022 | A | UFGS 13 48 73 Seismic Control For Nonstructural Components | May-2022 | R | Superseding UFGS 13 48 73 SEISMIC CONTROL FOR MECHANICAL EQUIPMENT without revision in response to CCR 11530. Nontechnical section title change. | |
| May-2022 | S | UFGS 22 15 09.00 40 General Service Compressed-Air Systems Cleaning Procedures | May-2022 | R | Revision: Update technical requirements, references and format. | |
| May-2022 | S | UFGS 23 01 30.41 HVAC System Cleaning | May-2022 | R | Revision: Update technical requirements, references and format. | |
| May-2022 | S | UFGS 23 05 15 Common Piping for HVAC | May-2022 | R | Revision: Update technical requirements, references format, and incorporate the following CCRs: 7186, 7266, 7343, 8631, 8858, 9386, 9765, 10198, 10295, 10931, 11252, 11341, 11342, 11343, 11344, 11486 | |
| May-2022 | S | UFGS 23 05 48.00 40 Vibration and Seismic Controls for HVAC Piping and Equipment | May-2022 | R | Revision: Update technical requirements, references format, and incorporate the following CCRs: 6858, 7126 | |
| May-2022 | N | UFGS 26 13 00 SF6/High-Firepoint Fluids Insulated Pad-Mounted Switchgear | May-2021 | C | 1 | Per CCR 8883, updated Automatic Switch Controls paragraph (2.1.4) with options for 120Vac control power. |
| May-2022 | A | UFGS 27 51 16 Public Address Systems | May-2020 | C | 1 | Incorporated CCR 4973 |
| May-2022 | N | UFGS 31 62 13.13 Cast-In-Place Concrete Piles | Apr-2006 | C | 2 | Per CCR 11703, removed reference to UFGS 00 22 13.00 20 in Measurement and Payment paragraph (1.2.2) |
| May-2022 | N | UFGS 31 62 13.20 Precast/Prestressed Concrete Piles | Nov-2020 | C | 1 | Per CCR 11704, removed reference to UFGS 00 22 13.00 20 in UNIT PRICE paragraph (1.6) |
| May-2022 | N | UFGS 31 62 13.24 Concrete Cylinder Piles | Nov-2020 | C | 1 | Per CCR 11705, removed reference to UFGS 00 22 13.00 20 in UNIT PRICE paragraph (1.6) |
| May-2022 | N | UFGS 31 62 13.26 Pressure-Injected Footings | Nov-2020 | C | 1 | Per CCR 11707, removed reference to UFGS 00 22 13.00 20 in Unit Price paragraph (1.4.3) |
| May-2022 | N | UFGS 31 62 16.13 Steel Pipe Piles | Nov-2020 | C | 1 | Removed reference to UFGS 00 22 13.00 20 in Unit Price paragraph (1.4.4) |
| May-2022 | N | UFGS 31 62 16.16 Steel H-Piles | Nov-2020 | C | 1 | Per CCR 11708, removed reference to UFGS 00 22 13.00 20 in Unit Price paragraph (1.4.3) |
| May-2022 | N | UFGS 31 62 19 Timber Piles | Nov-2020 | C | 1 | Per CCR 11709, removed reference to UFGS 00 22 13.00 20 in Unit Price paragraph (1.4.3) |
| May-2022 | N | UFGS 31 62 19.13 Timber Marine Piles | Nov-2016 | C | 2 | Per CCR 11710, removed reference to UFGS 00 22 13.00 20 in BASIS OF BIDS paragraph (1.5) |
| May-2022 | N | UFGS 31 62 50 Densified Aggregate Piers | Nov-2020 | C | 1 | Per CCR 11712, removed reference to UFGS 00 22 13.00 20 in Unit Price paragraph (1.4.3) |
| May-2022 | N | UFGS 31 63 26.60 [Grouted] Helical Piles | Nov-2020 | C | 1 | Per CCR 11716, removed reference to UFGS 00 22 13.00 20 in Unit Price paragraph (1.4.3) |
| May-2022 | A | UFGS 32 01 17.61 Sealing Cracks in Asphalt Paving | May-2022 | R | Complete review and update. | |
| May-2022 | A | UFGS 32 11 20 [Base Course for Rigid][ and ][Subbase] [Select-Material] [For Flexible Paving] | May-2022 | R | Complete review and update, including section title change from [BASE COURSE FOR RIGID][ AND ][SUBBASES FOR FLEXIBLE] PAVING to [BASE COURSE FOR RIGID][ AND ][SUBBASE] [SELECT-MATERIAL] [FOR FLEXIBLE PAVING]. | |
| May-2022 | A | UFGS 32 11 23 [Aggregate Base Course] [and][or] [Graded Crushed Aggregate Base Course] for Flexible Paving | May-2022 | R | Complete review and update, including section title change from AGGREGATE BASE COURSE to [AGGREGATE BASE COURSE] [AND/OR][GRADED CRUSHED AGGREGATE BASE COURSE] FOR FLEXIBLE PAVING. | |
| May-2022 | A | UFGS 32 12 15.13 Asphalt Paving for Airfields | Nov-2020 | C | 1 | In response to CCR 10561, added appropriate references for Navy and NASA associated with paragraphs CONTRACTOR QUALITY CONTROL STAFF, CONTRACTOR QUALITY CONTROL and GENERAL QUALITY CONTROL REQUIREMENTS. In response to CCR 11001 and CCR 9916, consolidated and clarified straightedge testing for longitudinal and transverse smoothness as well as revised Profilograph Testing requirements and associated acceptance Table 2. Prohibited the use of recycled asphalt shingles (RAS) in the asphalt mixture. |
| May-2022 | A | UFGS 33 51 43 Instrumentation and Performance Monitoring of Structures | May-2022 | N | New UFGS | |
| May-2022 | A | UFGS 35 20 20 Electrical Equipment for Gate Hoist | May-2022 | R | Complete review and update. | |
| May-2022 | A | UFGS 35 45 03.00 10 Speed Reducers for Storm Water Pumps | May-2022 | R | Complete review and update. | |
| May-2022 | N | UFGS 41 22 13.55 Bridge Cranes, Aircraft Maintenance Hangar | Feb-2022 | C | 1 | Added technical requirement to second text paragraph in subpart 2.3.2.2 Load Block and Hook |
| Feb-2022 | N | UFGS 01 14 00 Work Restrictions | Nov-2011 | C | 14 | In response to CCR 11282, "Naval Base, Norfolk VA" and "Naval Air Station, Norfolk, VA" changed to "Naval Station Norfolk, Norfolk, VA". |
| Feb-2022 | N | UFGS 01 35 13 Special Project Procedures | Nov-2020 | C | 1 | In response to CCR 9539, specifier notes were added to the Definitions and Airfield Obstruction Lights paragraphs; tailoring was corrected to NAVFAC HI for paragraphs 3.2.3 "RIMPAC", 3.2.4 "December 7, 1941", and 3.2.5 "Pearl Harbor" |
| Feb-2022 | N | UFGS 01 35 26 Governmental Safety Requirements | Nov-2020 | C | 3 | Added "Government Designated Authority (GDA)" to Dive Safety Requirements paragraph. In response to CCR 11124, updated first sentence in Competent Person, Cranes and Rigging paragraph. |
| Feb-2022 | N | UFGS 01 58 00 Project Identification | Aug-2019 | C | 1 | In reference to CCR 11189, Project Sign Details (PDF and zip files) found under Related Materials have been updated. Classified as a clerical change. |
| Feb-2022 | N | UFGS 08 32 13 Aluminum Sliding Glass Doors | Aug-2020 | C | 1 | In response to CCR 10477, bracket placement corrected to surround EXTRA STOCK paragraph (1.5) |
| Feb-2022 | S | UFGS 08 33 23 Overhead Coiling Doors | Aug-2020 | C | 1 | CCR10484: Adjusted tailoring option to entire portion of subpart 2.2.5 ELECTRIC DOOR OPERATORS |
| Feb-2022 | N | UFGS 08 51 23 Steel Windows | Aug-2020 | C | 1 | In response to CCR 10430, corrected specifier note for electrical CSI division, provided Army tailoring option for specific submittals within Submittal Article (1.2), and removed brackets from Thermal Performance paragraph (1.5.2) |
| Feb-2022 | N | UFGS 08 52 00 Wood Windows | Aug-2020 | C | 1 | In response to the following CCRs: 10475, 11217, and 11224, submittal item "Engineered Wood Products" has been tailored for NAVY in Submittal Article and corrected submittal tag with in the section text to the proper paragraph Engineered Wood Products (1.2.3). CCRs 10475 and 11225, removed brackets and NAVY tailoring for submittal item "Adhesives" to correct discrepancy since the Adhesives submittal paragraph (2.3.1) is not tailored. |
| Feb-2022 | N | UFGS 08 53 00 Plastic Windows | Aug-2020 | C | 1 | In response to CCR 10476, adjusted location of NAVY tailoring in Material Identification paragraph. |
| Feb-2022 | N | UFGS 08 56 46.10 20 Radio Frequency Shielded Enclosures, Demountable Type | Aug-2011 | C | 1 | In response to CCR 10407, corrected CSI division for Electrical in specifier note for Grounding paragraph (3.8) |
| Feb-2022 | N | UFGS 08 56 46.20 20 Radio Frequency Shielded Enclosures, Welded Type | Aug-2011 | C | 2 | In response to CCR 10408, corrected CSI division for Electrical in specifier note for Grounding paragraph (3.7) |
| Feb-2022 | N | UFGS 08 71 00 Door Hardware | Feb-2016 | C | 4 | In response to the following: CCR 9281, the Hardware Schedule Table (1.5) has been replaced with a hardware item list and a hardware schedule list; CCR 10303, deleted Texture paragraph (2.3.12.3) as it does not apply. |
| Feb-2022 | A | UFGS 23 30 00 HVAC Air Distribution | May-2020 | C | 1 | Incorporated CCR 2491. |
| Feb-2022 | N | UFGS 23 52 33.01 20 Steam Heating Plant Watertube (Shop Assembled) Coal/Oil or Coal | Nov-2008 | C | 3 | Under Related Requirements, "VAMS 23 09 53.00 20 CONTROLS AND INSTRUMENTATION BOILER PLANT" replaced with "UFC 3-430-11 BOILER PLANT INSTRUMENTATION AND CONTROL SYSTEMS"; also, the term "VAMS" has been removed throughout this section. |
| Feb-2022 | N | UFGS 23 52 33.02 20 Steam Heating Plant Watertube (Field Erected) Coal/Oil or Coal | Nov-2008 | C | 5 | The term "VAMS" has been removed throughout this section. |
| Feb-2022 | N | UFGS 23 52 33.03 20 Water-Tube Boilers, Oil/Gas or Oil | Nov-2008 | C | 4 | The term "VAMS" has been removed throughout this section. |
| Feb-2022 | N | UFGS 26 05 33 Dockside Power Connection Stations | Feb-2022 | R | Complete review; revised to incorporate CCRs. | |
| Feb-2022 | N | UFGS 33 11 00 Water Utility Distribution Piping | Feb-2018 | C | 1 | Changes made to incorporate multiple CCRs, including updating lead free and PE Pipe requirements and adding PE tubing. |
| Feb-2022 | A | UFGS 34 71 13.19 Crash Rated Active Vehicle Barriers and Controls | Feb-2020 | D | Superseded by UFGS 34 75 13.13 CRASH RATED ACTIVE VEHICLE BARRIERS AND CONTROLS. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Feb-2022 | A | UFGS 34 75 13.13 Crash Rated Active Vehicle Barriers And Controls | Feb-2022 | N | Superseding UFGS 34 71 13.19 CRASH RATED ACTIVE VEHICLE BARRIERS AND CONTROLS. | |
| Feb-2022 | A | UFGS 35 01 41.00 10 Electromechanical Operating Machinery for Locks and Dams | Aug-2020 | C | 1 | Incorporated CCR 10582. |
| Feb-2022 | A | UFGS 35 20 23.13 National Dredging Quality Management Program - Scow [Monitoring][ and ][Ullage] Profile | Feb-2022 | N | New UFGS. | |
| Feb-2022 | A | UFGS 35 20 23.23 National Dredging Quality Management Program - Hopper Dredge | Feb-2022 | N | New UFGS. | |
| Feb-2022 | A | UFGS 35 20 23.33 National Dredging Quality Management Program - Pipeline Hydraulic Dredge | Feb-2022 | N | New UFGS. | |
| Feb-2022 | N | UFGS 41 22 13.55 Bridge Cranes, Aircraft Maintenance Hangar | Feb-2022 | R | Complete review and update. Clarified terminology and made changes to submittals along with technical and testing requirements. | |
| Nov-2021 | N | UFGS 01 31 23.13 20 Electronic Construction and Facility Support Contract Management System (eCMS) | May-2017 | C | 7 | In response to CCR 11022, updated requirements for jobsite computer tablet in the Field Administration paragraph, and CCR 11023, updated the Contract Administration paragraph to clarify eCMS file storage structure. Also added minimum download and upload speeds to paragraph 1.4.1 General. |
| Nov-2021 | N | UFGS 01 35 26 Governmental Safety Requirements | Nov-2020 | C | 2 | In response to CCR 10735, corrected CFR reference in the Competent Person for Confined Space Entry paragraph and updated the Work Around Flammable Materials paragraph. |
| Nov-2021 | A | UFGS 01 45 00.00 10 Quality Control | Nov-2016 | C | 2 | Incorporated CCRs 8607, 10228, 10948, and 11035. |
| Nov-2021 | N | UFGS 01 58 00 Project Identification | Aug-2019 | C | 3 | In response to CCR 9882, instructions have been added for Air Force projects on Guam, on both Navy installation with NAVFAC execution and Army installation with USACE execution. Also, clarified Air Force instruction in the first Note in the Project Identification Signboard paragraph. |
| Nov-2021 | A | UFGS 01 74 19 Construction Waste Management and Disposal | Feb-2019 | C | 3 | Required to align with NAVFAC regional fidelity, and to fix administrative issues, per two CCRs. |
| Nov-2021 | A | UFGS 01 78 24.00 10 Facility Data Requirements | May-2018 | C | 1 | Incorporated CCR 10987 and corrected formatting issues. |
| Nov-2021 | N | UFGS 03 30 00 Cast-In-Place Concrete | Feb-2019 | C | 3 | In response to CCR 10400, updated paragraph 2.3.1.2 -Blended Cements, list item c. and 2.3.1.6-Other Supplementary Cementitious Materials. Also updated 3.6.2-Mixing, list item c. |
| Nov-2021 | N | UFGS 03 45 00 Precast Architectural Concrete | May-2016 | C | 2 | In response to CCR 9942 (submitted for UFGS-03 45 33), updated the table in the Cementitious Materials paragraph. |
| Nov-2021 | N | UFGS 03 45 33 Precast [Prestressed] Structural Concrete | May-2016 | C | 1 | In response to CCR 9942, updated the table in the Cementitious Materials paragraph. Also updated the MATERIALS paragraph. |
| Nov-2021 | N | UFGS 08 34 16.10 Horizontal Rolling Steel Doors | Nov-2021 | R | General periodic update to include new rolling steel door technologies, materials, resiliency, and design methodologies to increase door performance and industry competition. Title changed from STEEL SLIDING HANGAR DOORS. | |
| Nov-2021 | N | UFGS 08 34 16.20 Vertical Lift Fabric Doors | Aug-2021 | C | 1 | Targeted update to incorporate recent lessons learned for wire-rope termination, safety arresters, performance standards, warranty and other safety items. |
| Nov-2021 | N | UFGS 08 34 49.00 20 Hemp Shielded Door | Nov-2021 | R | Complete review and update including CCR 921. | |
| Nov-2021 | A | UFGS 09 97 02 Painting: Hydraulic Structures | Feb-2020 | C | 1 | Incorporated CCRs and corrected formatting errors. |
| Nov-2021 | N | UFGS 26 08 00 Apparatus Inspection and Testing | Nov-2021 | R | Complete review and revision including CCRs 7038 and 8614. | |
| Nov-2021 | N | UFGS 26 11 13.00 20 Primary Unit Substation | Nov-2021 | R | Complete review and revision. | |
| Nov-2021 | A | UFGS 26 11 14.00 10 Main Electric Supply Station and Substation | Nov-2021 | R | Complete review and update. | |
| Nov-2021 | N | UFGS 26 11 16 Secondary Unit Substations | Nov-2021 | R | Complete review and revision. | |
| Nov-2021 | N | UFGS 26 13 13 Metal-Clad Switchgear | Nov-2021 | N | New section to address the requirements for metal-clad switchgear rated 1000 volts and above. | |
| Nov-2021 | N | UFGS 26 13 14 Switchgear House | Nov-2021 | N | New section to address the requirements for environmentally controlled, exterior prefabricated, pre-engineered structures to house a coordinated grouping of electrical switchgear and associated power and control equipment. | |
| Nov-2021 | N | UFGS 26 20 00 Interior Distribution System | Aug-2019 | C | 3 | In response to the following: CCR 10728, "Cable Trays" and optional "Cable Tray Design Data" were added to the Submittal Article under SD-03 and SD-05, respectively, and tagged in the CABLE TRAY paragraph; CCR 10729, optional text added for the cable tray to serve as the EGC in the Trough-Type Cable Trays, Ladder-Type Cable Trays, and Channel-Type Cable Trays paragraphs; and CCR 10730, able Tray Installation paragraph has been updated to prevent partial or complete obstruction of access by cable tray and tray supports. |
| Nov-2021 | N | UFGS 26 31 00 Facility-Scale Solar Photovoltaic (PV) Systems | Nov-2021 | R | Complete review and revision including title change from SOLAR PHOTOVOLTAIC (PV) COMPONENTS. | |
| Nov-2021 | N | UFGS 26 51 00 Interior Lighting | May-2020 | C | 2 | In response to the following: CCR 10008, changed the LED source replacement requirement from 10% to 15% in the Luminaire Warranty paragraph (list items b and c) and CCR 10327, the integral driver surge protection has been updated to 2 kV in the LED Drivers paragraph, list item f. |
| Nov-2021 | N | UFGS 27 21 00.00 20 Intercommunication System | Apr-2006 | D | Superseded by UFGS-27 51 23 INTERCOMMUNICATION SYSTEM. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Nov-2021 | S | UFGS 27 21 00.00 40 Intercommunication System | Feb-2016 | D | Superseded by new unified UFGS 27 51 23 INTERCOMMUNICATION SYSTEM. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Nov-2021 | N | UFGS 27 41 00 Audio-Visual Systems | Nov-2021 | N | New section to address the requirements for most audio-visual system projects. | |
| Nov-2021 | N | UFGS 27 51 23 Intercommunication System | Nov-2021 | N | New unified section superseding UFGS-27 21 00.00 20, UFGS-27 21 00.00 40, and UFGS-27 51 23.10 all titled INTERCOMMUNICATION SYSTEM. | |
| Nov-2021 | A | UFGS 27 51 23.10 Intercommunication System | May-2011 | D | Superseded by new unified UFGS 27 51 23 INTERCOMMUNICATION SYSTEM. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Nov-2021 | A | UFGS 31 23 00.00 Tunnel Excavation – Blasting | Nov-2021 | N | New UFGS. | |
| Nov-2021 | A | UFGS 31 23 01 Underwater Blasting | Feb-2021 | C | 1 | Incorporated CCR 10552 and corrected formatting errors. |
| Nov-2021 | A | UFGS 31 23 06.00 Blasting - Surface | Feb-2021 | C | 1 | Incorporated CCR 10553 and corrected formatting errors. |