History: Below is a listing of the Revisions and Changes made to this UFGS.
KEY | PREPARING ACTIVITY (PA) | A Army | N Navy | F Air Force | S NASA [ARCHIVED] |
---|---|---|---|---|---|
ACTION | N New | R Revision | C Change | D Deletion |
Release | PA | Date | Action | Change # | Nature of Change or Revision |
---|---|---|---|---|---|
Aug-2025 | N | Aug-2022 | C | 2 | In response to CCR 16848, updated Recyclables paragraph (1.2.20.6). |
May-2025 | N | Aug-2022 | C | 1 | In response to the following: CCR 14366, replaced "Safety Plan" with "Accident Prevention Plan (APP)" in HAZARDOUS MATERIAL MANAGEMENT paragraph (1.3.8); CCR 14378, updated Protection of the Environment from Waste Derived from Contractor Operations paragraph (1.7.6); CCR 14380, added additional environmental requirements for NW region to align with new environmental regulations; CCRs 14410, 14411, and 14412, updated Cuba's requirement in Parts 2 and 3; CCR 14528, added new WASHINGTON tailoring for Location Specific Universal Waste paragraph (1.2.26); CCR 14539, added 40 CFR 372 to REFERENCES; CCR 14658 updated Submittal Article; CCR 15470, added brackets and Note to Documentation paragraph (1.7.2.3); and CCRs 15851 & 16065, added 'Critical Root Zone' definition. |
Aug-2022 | N | Aug-2022 | R | Revised to align with current industry standards and DoD requirements. This Section supersedes UFGS-01 57 19.00 20 Supplemental Temporary Environmental Controls as all requirements are contained within this Tri-Service, tailorable specification as reorganized paragraphs in a hierarchical presentation. | |
Aug-2021 | N | Nov-2015 | C | 5 | Added Note to Submittal Article with instructions for Navy Design-Build projects. In response to CCR 10213, updated requirements for NAVFAC PAC DB and DBB in Environmental Protection Plan paragraph. |
Aug-2020 | N | Nov-2015 | C | 4 | In response to CCR 8832, changes to submittal requirements for NAVFAC PAC to mitigate schedule impacts: added Note under Submittal Article SD-01 and paragraph "ENVIRONMENTAL PROTECTION PLAN" (1.7); under paragraphs "Stormwater Pollution Prevention Plan" (3.2.1.1) and "Stormwater Notice of Intent for Construction Activities" (3.2.1.2) added note and text. |
Aug-2019 | N | Nov-2015 | C | 3 | In response to the following CCRs: #5233 - revised language in paragraph "Dust Control" (3.5.7) to reflect the Crystalline Silica hazard associated with cement and concrete products per the new OSHA Standard of Crystalline Silica; #5733 - "Stormwater Pollution Prevention Plan" has been added as a submittal item under SD-01 and in paragraph "Stormwater Pollution Prevention Plan" (3.2.1.1); #7178 - revision to clarify submittal item "Solid Waste Management Report", updated as "Monthly Solid Waste Disposal Report" in Part 1 (1.11.1) and "Project Solid Waste Disposal Documentation Report" in Part 3 (3.7.2.1) and in the Submittal Article under SD-06 and SD-11 respectively; #7179 - added a new row "C&D Debris Composted" to table under paragraph Nonhazardous Solid Waste Diversion Report (3.6.2) |
May-2019 | N | Nov-2015 | C | 2 | In response to CCR 7194, FAR clause 52.242-14 Suspension of Work was added to the paragraph "Non-Compliance Notifications"; updated links per CCRs 7375 and 7376 |
Aug-2016 | N | Nov-2015 | C | 1 | Fixed bracketed items and tailoring. |
Nov-2015 | N | Nov-2015 | N | Unification of the following sections and update to current requirements: 01 57 19.00 20 TEMPORARY ENVIRONMENTAL CONTROLS, 01 57 20.00 10 ENVIRONMENTAL PROTECTION, 01 57 23 TEMPORARY STORMWATER POLLUTION CONTROL, and 01 57 16 TEMPORARY PEST CONTROL |