Oct-2007 A UFGS 04 20 00 Unit Masonry R Updated seismic criteria
Oct-2007 A UFGS 04 21 13.13 Nonbearing Masonry Veneer/Steel Stud Walls R Updated seismic criteria
Oct-2007 N UFGS 05 12 00 Structural Steel R Updated AISC categories
Oct-2007 A UFGS 07 84 00 Firestopping R Updated seismic criteria
Oct-2007 N UFGS 08 71 00 Door Hardware R Corrected paragraph entitled "Texture."
Oct-2007 A UFGS 09 51 00 Acoustical Ceilings R Updated seismic criteria
Oct-2007 A UFGS 10 22 26 Operable Partitions D Superseded by UFGS 10 22 26.33 Folding Panel Partitions and UFGS 10 22 26.43 Sliding Partitions.
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Oct-2007 N UFGS 10 22 26.13 Accordion Folding Partitions R Added NASA requirements
Oct-2007 N UFGS 10 22 26.23 Coiling Partitions N New section
Oct-2007 A UFGS 10 22 26.33 Folding Panel Partitions N New section; Superseding UFGS 10 22 26 Operable Partitions
Oct-2007 A UFGS 10 22 26.43 Sliding Partitions N New section; Superseding UFGS 10 22 26 Operable Partitions
Oct-2007 A UFGS 11 24 27 Air Stripper R Updated seismic criteria
Oct-2007 A UFGS 11 46 01.00 10 Food Service Equipment R Revised in response to CCR's 1158 and 2063
Oct-2007 A UFGS 11 82 20 Incinerators, General Purpose R Updated seismic criteria
Oct-2007 A UFGS 11 82 21 Medical Waste Incinerators R Updated seismic criteria
Oct-2007 A UFGS 13 27 54.00 10 Electromagnetic (EM) Shielding R Updated seismic criteria
Oct-2007 A UFGS 13 34 20 Metal Building Systems (Minor Requirements) R Updated seismic criteria
Oct-2007 A UFGS 13 48 00.00 10 Seismic Protection for Mechanical Equipment R Updated seismic criteria
Oct-2007 A UFGS 14 24 00 Hydraulic Elevators R Updated seismic criteria
Oct-2007 A UFGS 21 13 13.00 10 Wet Pipe Sprinkler System, Fire Protection R Updated seismic criteria
Oct-2007 A UFGS 21 13 17.00 10 Dry Pipe Sprinkler System, Fire Protection R Updated seismic criteria
Oct-2007 A UFGS 21 13 18.00 10 Preaction and Deluge Sprinkler Systems, Fire Protection R Updated seismic criteria
Oct-2007 A UFGS 21 13 24.00 10 Aqueous Film-Forming Foam (AFFF) Fire Protection System R Updated seismic criteria
Oct-2007 A UFGS 22 04 00.00 10 Plumbing, Hospital R Updated seismic criteria
Oct-2007 A UFGS 22 33 30.00 10 Solar Water Heating Equipment R Updated seismic criteria
Oct-2007 A UFGS 23 07 00 Thermal Insulation for Mechanical Systems R General revisions for pipe, duct and equipment
Oct-2007 N UFGS 23 08 00.00 20 Commissioning of Mechanical[ and Plumbing] Systems R Change to paragraph entitled "Testing" (3.1.3)
Oct-2007 A UFGS 23 10 00 Fuel Storage Systems R Updated seismic criteria
Oct-2007 A UFGS 23 11 23.00 10 Gas Piping System N Superseding UFGS 33 51 01.00 10 with same title
Oct-2007 A UFGS 23 23 00 Refrigerant Piping R Updated seismic criteria
Oct-2007 N UFGS 23 30 13.00 20 Ductwork and Ductwork Accessories D Superseded by UFGS 23 00 00 Air Supply, Distribution, Ventilation, and Exhaust Systems.
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Oct-2007 N UFGS 23 34 16.00 20 Air Handling Units D Superseded by UFGS 23 00 00 Air Supply, Distribution, Ventilation, and Exhaust Systems.
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Oct-2007 A UFGS 23 40 00.00 10 Chemical, Biological, and Radiological (CBR) Air Filtration System R Updated seismic criteria
Oct-2007 A UFGS 23 52 00.00 10 Water and Steam Heating; Oil, Gas or Both; Up to 20 MBTUH R Revised in response to CCR's 1574, 1577, 1582 and 1583
Oct-2007 A UFGS 23 52 43.00 10 Heat Recovery Boilers R Updated seismic criteria
Oct-2007 A UFGS 23 54 16.00 10 Heating System; Gas-Fired Heaters R Updated seismic criteria
Oct-2007 A UFGS 23 57 10.00 10 Forced Hot Water Heating Systems Using Water and Steam Heat Exchangers R Updated seismic criteria
Oct-2007 A UFGS 23 63 00.00 10 Cold Storage Refrigeration Systems R Revised in response to CCR 1590
Oct-2007 A UFGS 23 64 00.00 10 Liquid Chillers R Revised in response to CCR 1585
Oct-2007 A UFGS 23 70 01.00 10 Central Steam-Generating System, Coal-Fired R Updated seismic criteria
Oct-2007 A UFGS 23 70 02.00 10 Central Steam Generating System - Combination Gas and Oil Fired R Updated seismic criteria
Oct-2007 A UFGS 23 70 03.00 10 Heating and Utilities Systems, Central Steam R Updated seismic criteria
Oct-2007 A UFGS 23 72 00 Energy Recovery Systems R Updated seismic criteria [23 72 00.00 10]
Oct-2007 A UFGS 23 82 02.00 10 Unitary Heating and Cooling Equipment R Revised in response to CCR's 1591, 1592 and 1593
Oct-2007 A UFGS 26 05 48.00 10 Seismic Protection for Electrical Equipment R Updated seismic criteria
Oct-2007 A UFGS 26 11 14.00 10 Main Electric Supply Station and Substation R Updated seismic criteria
Oct-2007 A UFGS 26 22 00.00 10 480-Volt Station Service Switchgear and Transformers R Revised metrication
Oct-2007 F UFGS 26 27 13.10 30 Electric Meters N New section
Oct-2007 A UFGS 26 28 00.00 10 Motor Control Centers, Switchboards and Panelboards R Revised metrication
Oct-2007 A UFGS 26 28 01.00 10 Coordinated Power System Protection R Updated seismic criteria
Oct-2007 A UFGS 26 32 14.00 10 Diesel-Generator Set, Stationary 15-300 KW, Standby Applications R Updated seismic criteria
Oct-2007 A UFGS 26 32 15.00 10 Diesel-Generator Set Stationary 100-2500 KW, with Auxiliaries R Updated seismic criteria
Oct-2007 A UFGS 26 32 33.00 10 Uninterruptible Power Supply (UPS) System Above 15 KVA Capacity R Updated seismic criteria
Oct-2007 N UFGS 26 32 33.00 20 Installation of Uninterruptible Power Supply (UPS) D Superseded by UFGS 26 33 53.00 20 Uninterruptible Power Supply (UPS).
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Oct-2007 N UFGS 26 33 53.00 20 Uninterruptible Power Supply (UPS) N Superseding UFGS 26 32 33.00 20 Installation of Uninterruptible Power Supply (UPS)
Oct-2007 A UFGS 26 36 00.00 10 Automatic Transfer Switch and By-Pass/Isolation Switch R Updated seismic criteria
Oct-2007 A UFGS 26 54 21.00 10 Helipad Lighting and Visual Navigation Aids R Revised metrication
Oct-2007 A UFGS 26 55 53.00 10 Exterior Lighting Including Security and CCTV Applications R Revised metrication
Oct-2007 A UFGS 26 56 20.00 10 Airfield and Heliport Lighting and Visual Navigation Aids R Revised metrication
Oct-2007 A UFGS 27 52 32.00 10 Nurse Call Tone-Visual (NCTV) System R Revised metrication
Oct-2007 A UFGS 28 20 01.00 10 Electronic Security System R Updated seismic criteria
Oct-2007 N UFGS 28 31 63.00 20 Analog/Addressable Interior Fire Alarm System R Clarified paragraph entitled "Repair Service/Replacement Parts" (paragraph 2.1.2).
Oct-2007 A UFGS 31 21 00 Off-Gassing Mitigation R Updated seismic criteria
Oct-2007 A UFGS 31 62 16.00 10 Steel H-Piles R Updated seismic criteria
Oct-2007 A UFGS 31 62 20.00 10 Round Timber Piles R Updated seismic criteria
Oct-2007 A UFGS 31 62 23.13 Concrete-Filled Steel Piles R Updated seismic criteria
Oct-2007 A UFGS 31 63 16 Augered Cast-In-Place Piles R Updated seismic criteria
Oct-2007 A UFGS 31 63 26.00 10 Drilled Foundation Caissons (Piers) R Updated seismic criteria
Oct-2007 A UFGS 32 13 14 Concrete Pavement for Small Projects D Replaced/Superseded by UFGS 32 13 13.03 Airfields and Heavy Duty Concrete Pavement Less Than 10000 Cubic Yards.
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Oct-2007 A UFGS 32 32 23 Segmental Concrete Block Retaining Wall R Updated seismic criteria
Oct-2007 A UFGS 33 16 15 Water Storage Steel Tanks R Updated seismic criteria
Oct-2007 A UFGS 33 51 01.00 10 Gas Piping Systems D Renamed/Superseded by UFGS 23 11 23.00 10 with same title.
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Oct-2007 A UFGS 33 52 44 Aviation Fueling Systems R Updated seismic criteria
Oct-2007 N UFGS 33 52 80 Liquid Fuels Pipeline Coating Systems N New section
Oct-2007 A UFGS 33 60 00.00 10 Central High Temperature Water (HTW) Generating Plant and Auxiliaries R Updated seismic criteria
Oct-2007 A UFGS 33 70 02.00 10 Electrical Distribution System, Underground R Updated seismic criteria
Oct-2007 A UFGS 33 82 01 Intercommunication System R Revised metrication
Oct-2007 A UFGS 40 05 13 Pipelines, Liquid Process Piping R Updated seismic criteria
Oct-2007 A UFGS 40 95 00 Process Control R Updated seismic criteria
Oct-2007 A UFGS 41 65 10.00 10 [Diesel] [Natural Gas] Fueled Engine Pump Drives R Updated seismic criteria
Oct-2007 A UFGS 43 11 00 Fans/Blowers/Pumps; Off-Gas R Updated seismic criteria
Oct-2007 A UFGS 43 13 13.13 Vapor Phase Activated Carbon Adsorption Units R Updated seismic criteria
Oct-2007 A UFGS 43 31 13.14 Downflow Liquid Activated Carbon Adsorption Units R Updated seismic criteria
Oct-2007 A UFGS 44 10 00 Air Pollution Control R Updated seismic criteria
Oct-2007 A UFGS 44 11 33 Thermal (Catalytic) Oxidation Systems R Updated seismic criteria
Oct-2007 A UFGS 44 41 13 Prefabricated Biochemical Wastewater Treatment Plant R Updated seismic criteria
Oct-2007 A UFGS 44 43 00 Filtration System R Updated seismic criteria
Oct-2007 A UFGS 44 44 53 Advanced Oxidation Processes (AOP) R Updated seismic criteria
Oct-2007 A UFGS 44 46 19 Sludge-Digester Gas, Heating, and Mixing System R Updated seismic criteria
Jul-2007 N UFGS 01 11 00 Summary of Work R Corrected hyperlink to CCB.
Jul-2007 N UFGS 01 14 00 Work Restrictions R Added paragraph on smoking policy.
Jul-2007 A UFGS 01 32 01.00 10 Project Schedule R Revised in response to CCRs 1117 and 1120; submittal paragraph added
Jul-2007 S UFGS 01 35 23.00 40 Owner Safety Requirements R Reference Update
Jul-2007 N UFGS 01 45 01.00 20 Quality Control (QC) - Minor Construction R Modified requirements for submitting reports on contracts and task orders less than $750K
Jul-2007 S UFGS 01 60 00.00 40 Product Requirements D Redundant, section deleted.
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Jul-2007 S UFGS 03 30 00.00 40 Cast-in-Place Concrete R Reference and Section References (SRF) update
Jul-2007 S UFGS 03 30 53.00 40 Miscellaneous Cast-in-Place Concrete R Reference Update
Jul-2007 S UFGS 03 30 53.00 40 Miscellaneous Cast-in-Place Concrete R Reference Update
Jul-2007 S UFGS 03 45 00.00 40 Precast Architectural Concrete R Reference Update
Jul-2007 S UFGS 03 45 00.00 40 Precast Architectural Concrete R Reference Update