Below is a listing of the Revisions and Changes made to UFGS Sections for each release. You can narrow the list by selecting a UFGS Release date from the drop-down and clicking 'Apply'.
| KEY | PREPARING ACTIVITY (PA) | A Army | N Navy | F Air Force | S NASA [ARCHIVED] |
|---|---|---|---|---|---|
| ACTION | N New | R Revision | C Change | D Deletion |
| Release | PA | UFGS Section | Date | Action | Change # | Nature of Change or Revision |
|---|---|---|---|---|---|---|
| May-2014 | N | UFGS 01 57 19.01 20 Supplemental Temporary Environmental Controls | Feb-2010 | C | 3 | Modified subpart 3.1.1.1 |
| May-2014 | N | UFGS 01 78 24.00 20 Facility Data Workbook (FDW) | May-2014 | R | Revised "eOMSI documents" to "eOMSI Manual", revised "eOMSI Facility data" to "eOMSI Facility Data Workbook" and revised throughout to coordinate requirements. | |
| May-2014 | A | UFGS 03 11 13.00 10 Structural Cast-In-Place Concrete Forming | May-2014 | R | Major revision to comply with ICC IBC 2012 | |
| May-2014 | A | UFGS 03 11 19.00 Insulating Concrete Forming | May-2014 | R | Major revision to comply with ICC IBC 2012 | |
| May-2014 | A | UFGS 03 15 00.00 10 Concrete Accessories | May-2014 | R | Major revision to comply with ICC IBC 2012 | |
| May-2014 | A | UFGS 03 20 00.00 10 Concrete Reinforcing | May-2014 | R | Major revision to comply with ICC IBC 2012 | |
| May-2014 | N | UFGS 03 30 00 Cast-In-Place Concrete | May-2014 | R | Major revision to comply with IBC 2012 | |
| May-2014 | A | UFGS 03 30 00.00 10 Cast-In-Place Concrete | May-2014 | R | Major revision to comply with ICC IBC 2012 | |
| May-2014 | A | UFGS 03 30 53 Miscellaneous Cast-In-Place Concrete | May-2014 | R | Major revision to comply with ICC IBC 2012 | |
| May-2014 | A | UFGS 03 31 01.00 10 Cast-In-Place Structural Concrete for Civil Works | May-2014 | R | Major revision to comply with ICC IBC 2012 | |
| May-2014 | A | UFGS 03 35 00.00 10 Concrete Finishing | May-2014 | R | Major revision to comply with ICC IBC 2012 | |
| May-2014 | A | UFGS 03 39 00.00 10 Concrete Curing | May-2014 | R | Major revision to comply with ICC IBC 2012 | |
| May-2014 | S | UFGS 03 41 33 Precast Structural Pretensioned Concrete | Feb-2011 | C | 2 | SRF update, changed 05 05 23 WELDING, STRUCTURAL to 05 05 23.16 STRUCTURAL WELDING |
| May-2014 | S | UFGS 03 47 13 Tilt-Up Concrete | Aug-2008 | C | 2 | SRF update, changed 05 05 23 WELDING, STRUCTURAL to STRUCTURAL WELDING |
| May-2014 | A | UFGS 05 05 23 Welding, Structural | Nov-2008 | D | Superseded by UFGS 05 05 23.16 Structural Welding for compliance with MasterFormat. Also, major revision to comply with ICC IBC 2012. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| May-2014 | A | UFGS 05 05 23.13 10 Ultrasonic Inspection of Weldments | May-2014 | R | Major revision to comply with ICC IBC 2012 | |
| May-2014 | A | UFGS 05 05 23.16 Structural Welding | May-2014 | N | Superseding UFGS 05 05 23 Welding, Structural for compliance with MasterFormat. Section also updated to comply with ICC IBC 2012 | |
| May-2014 | N | UFGS 05 12 00 Structural Steel | May-2014 | R | Major revision to comply with IBC 2012 | |
| May-2014 | A | UFGS 05 50 14 Structural Metal Fabrications | May-2014 | R | Major revision to comply with ICC IBC 2012 | |
| May-2014 | A | UFGS 05 50 15 Civil Works Fabrications | May-2014 | R | Major revision to comply with ICC IBC 2012 | |
| May-2014 | S | UFGS 05 51 00 Metal Stairs | Feb-2012 | C | 1 | SRF update, changed 05 05 23 WELDING, STRUCTURAL to 05 05 23.16 STRUCTURAL WELDING. |
| May-2014 | S | UFGS 05 52 00 Metal Railings | Feb-2011 | C | 3 | SRF update, changed 05 05 23 WELDING, STRUCTURAL to STRUCTURAL WELDING |
| May-2014 | A | UFGS 07 05 23 Pressure Testing an Air Barrier System for Air Tightness | May-2014 | N | Superseding UFGS 07 08 27.00 10 Building Air Barrier System Testing for Commissioning | |
| May-2014 | A | UFGS 07 08 27.00 10 Building Air Barrier System Testing for Commissioning | Feb-2013 | D | Superseded by UFGS 07 05 23 Pressure Testing an Air Barrier System for Air Tightness and UFGS 07 27 10.00 10 Building Air Barrier System. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| May-2014 | A | UFGS 07 27 10.00 10 Building Air Barrier System | May-2014 | N | Superseding UFGS 07 08 27.00 10 Building Air Barrier System Testing for Commissioning | |
| May-2014 | A | UFGS 07 55 00 Protected Membrane Roofing (PMR) | Aug-2009 | C | 1 | Energy efficiency requirements added |
| May-2014 | N | UFGS 08 34 16.20 Vertical Lift Fabric Doors | May-2014 | R | Major revision; state-of-the-art study to improve VLFD reliability, improve performance requirements and increase vendor competitiveness. | |
| May-2014 | N | UFGS 08 53 00 Plastic Windows | Aug-2011 | C | 1 | Modified subpart 1.6.3 |
| May-2014 | N | UFGS 08 88 58 Air Traffic Control Tower Cab Glass | May-2014 | N | New section | |
| May-2014 | A | UFGS 11 44 00 Food Cooking Equipment | Jan-2008 | C | 1 | Energy efficiency requirements added |
| May-2014 | S | UFGS 28 05 26.00 40 Grounding and Bonding For Electronic Safety and Security | Aug-2013 | C | 1 | SRF update, changed 05 05 23 WELDING, STRUCTURAL to 05 05 23.16 STRUCTURAL WELDING |
| May-2014 | N | UFGS 32 17 23.00 20 Pavement Markings | Apr-2006 | C | 1 | Modified subpart 2.1 (note), 2.1.1 and 2.1.2. |
| May-2014 | A | UFGS 33 52 43 Aviation Fuel Distribution (Non-Hydrant) | May-2011 | C | 1 | Clarified washer material requirements as noted in CCR 2605 |
| May-2014 | A | UFGS 33 52 43.13 Aviation Fuel Piping | Feb-2010 | C | 1 | Clarified washer material requirements as noted in CCR 2604 |
| May-2014 | A | UFGS 35 01 43 Wire Rope for Gate Operating Devices | Apr-2008 | D | In combination with a major revision, section number changed for compliance with MasterFormat. Superseded by UFGS 35 01 70.13 Wire Rope for Gate Operating Devices. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| May-2014 | A | UFGS 35 01 70.13 Wire Rope for Gate Operating Devices | May-2014 | N | Major revision of and superseding UFGS 35 01 43 Wire Rope for Gate Operating Devices | |
| May-2014 | A | UFGS 35 05 40.14 10 Hydraulic Power Systems for Civil Works Structures | May-2014 | N | Major revision of and superseding UFGS 41 24 27.00 10 Hydraulic Power Systems for Civil Works Structures | |
| May-2014 | A | UFGS 35 05 40.17 Self-Lubricated Materials, Fabrication, Handling, and Assembly | May-2014 | N | New UFGS section | |
| May-2014 | S | UFGS 40 17 30.00 40 Welding General Piping | Aug-2010 | C | 2 | SRF update, changed 05 05 23 WELDING, STRUCTURAL to 05 05 23.16 STRUCTURAL WELDING |
| May-2014 | A | UFGS 41 24 27.00 10 Hydraulic Power Systems for Civil Works Structures | Jan-2008 | D | In combination with a major revision, section number changed for compliance with MasterFormat. Superseded by UFGS 35 05 40.14 10 Hydraulic Power Systems for Civil Works Structures. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| May-2014 | A | UFGS 48 06 15 Turbine Oil | May-2014 | N | Full review, updates and superseding UFGS 48 13 19.00 10 Turbine Oil | |
| May-2014 | A | UFGS 48 13 19.00 10 Turbine Oil | Nov-2008 | D | Superseded by UFGS 48 06 15 Turbine Oil. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Feb-2014 | N | UFGS 00 22 13 Supplementary Instructions to Bidders | May-2011 | D | Superseded by UFGS 00 22 13.00 20 Supplementary Instructions to Offerors Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Feb-2014 | N | UFGS 00 73 01 Supplementary Conditions for Guantanamo Bay Projects | Aug-2008 | C | 1 | Deleted subpart 1.3.1.3 "Waiver for Workers' Compensation" |
| Feb-2014 | A | UFGS 01 42 15 Metric Measurements | Feb-2014 | N | New; Revision of UFGS 00 31 10 Metric Measurements which was deleted August 2013. Section is being reinstated and has been renumbered. | |
| Feb-2014 | N | UFGS 01 57 19.01 20 Supplemental Temporary Environmental Controls | Feb-2010 | C | 2 | Modified note before Part 1, Part 1, subparts 1.3, 1.4.1, 1.4.1.2,1.4.1.2.2, 1.4.1.3, 1.4.1.4, 1.4.1.5, 1.4.1.6.1, 1.4.1.6.6, 1.4.1.7, 1.6.5.2.1 and 1.6.5.2.2 |
| Feb-2014 | N | UFGS 07 21 23 Loose Fill Thermal Insulation | May-2011 | C | 2 | Modified subpart 2.1.1 |
| Feb-2014 | N | UFGS 08 11 13 Steel Doors and Frames | Feb-2010 | C | 1 | Modified subpart 2.3 |
| Feb-2014 | A | UFGS 09 68 00 Carpeting | Nov-2013 | C | 1 | Allowed for use of triexta (PTT) |
| Feb-2014 | S | UFGS 12 48 13 Entrance Floor Mats and Frames | Feb-2014 | N | Superseding UFGS 12 48 13.13 Entrance Floor Mats; title and section number changed; updated entire section through unification; Tri Annual Database Maintenance (TADM) completed including incorporating CCRs | |
| Feb-2014 | S | UFGS 12 48 13.13 Entrance Floor Mats | Feb-2011 | D | Superseded by UFGS 12 48 13 Entrance Floor Mats and Frames Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Feb-2014 | S | UFGS 22 15 09.00 40 General Service Compressed-Air Systems Cleaning Procedures | Feb-2014 | R | Tri Annual Database Maintenance (TADM) completed | |
| Feb-2014 | A | UFGS 23 00 00 Air Supply, Distribution, Ventilation, and Exhaust Systems | Aug-2010 | C | 2 | Minimum frame length when Duct Height Greater than 300 mm (12 inches) revised to 127 mm (5 inches) |
| Feb-2014 | S | UFGS 23 05 15 Common Piping for HVAC | Feb-2014 | R | Tri Annual Database Maintenance (TADM) completed | |
| Feb-2014 | A | UFGS 23 09 23 LonWorks Direct Digital Control for HVAC and Other Building Control Systems | May-2011 | C | 1 | QC Checklist in APPENDIX A made available in electronic format for use with this section at: http://www.wbdg.org/ccb/NAVGRAPH/graphtoc.pdf |
| Feb-2014 | S | UFGS 23 22 13.35 40 Steam Traps | Feb-2014 | R | Tri Annual Database Maintenance (TADM) completed | |
| Feb-2014 | S | UFGS 26 05 71.00 40 Low-Voltage Overcurrent Protective Devices | Feb-2014 | R | Tri Annual Database Maintenance (TADM) completed | |
| Feb-2014 | N | UFGS 26 20 00 Interior Distribution System | Feb-2014 | R | Major revision | |
| Feb-2014 | A | UFGS 26 55 53.00 10 Exterior Lighting Including Security and CCTV Applications | Oct-2007 | D | Superseded by UFGS 26 56 00 through unification Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Feb-2014 | S | UFGS 28 33 00.00 40 Fuel-Gas Detection and Alarm | Feb-2014 | R | Tri Annual Database Maintenance (TADM) completed | |
| Feb-2014 | N | UFGS 33 11 00 Water Utility Distribution Piping | Feb-2011 | C | 3 | Modified subparts 2.2.1.3, 3.1.3.2, 3.2.2, 3.2.3; added 3.2.2.1 and 3.2.2.2 |
| Feb-2014 | A | UFGS 33 70 02.00 10 Electrical Distribution System, Underground | Nov-2008 | D | Superseded by UFGS 33 71 02 Underground Electrical Distribution through unification Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Feb-2014 | N | UFGS 33 71 02 Underground Electrical Distribution | Feb-2014 | N | New; Superseding UFGS 33 71 02.00 20 Underground Electrical Distribution and UFGS 33 70 02.00 10 Electrical Distribution System, Underground | |
| Feb-2014 | N | UFGS 33 71 02.00 20 Underground Electrical Distribution | Aug-2008 | D | Superseded by UFGS 33 71 02 Underground Electrical Distribution through unification Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Nov-2013 | S | UFGS 01 33 00 Submittal Procedures | May-2011 | C | 3 | Section 26 12 19.20 was replaced by 26 12 21 SINGLE-PHASED PAD- MOUNTED TRANSFORMERS at Subpart 1.5.1.2 |
| Nov-2013 | S | UFGS 01 78 24.00 20 Facility Data Workbook (FDW) | Aug-2012 | C | 1 | Revised note before part 1. |
| Nov-2013 | A | UFGS 02 65 00 Underground Storage Tank Removal | Feb-2010 | C | 1 | Removed references to EM 200-1-3 |
| Nov-2013 | A | UFGS 09 06 90 Schedules for Painting and Coating | May-2009 | C | 1 | Reformatting |
| Nov-2013 | A | UFGS 09 30 00 Ceramic Tile, Quarry Tile, and Paver Tile | Aug-2010 | D | Superseded by UFGS 09 30 13 Ceramic Tiling. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Nov-2013 | A | UFGS 09 30 13 Ceramic Tiling | Nov-2013 | N | Superseding UFGS 09 30 00 Ceramic Tile, Quarry Tile, and Paver Tile | |
| Nov-2013 | A | UFGS 09 68 00 Carpeting | Nov-2013 | R | Revised section title to comply with MasterFormat. Routine section maintenance. | |
| Nov-2013 | S | UFGS 12 32 00 Manufactured Wood Casework | Nov-2013 | R | Tri-Annual Database Maintenance (TADM) completed | |
| Nov-2013 | S | UFGS 12 32 00 Manufactured Wood Casework | Nov-2013 | R | Tri-Annual Database Maintenance (TADM) completed | |
| Nov-2013 | S | UFGS 21 21 00.00 40 Carbon-Dioxide Fire Extinguishing Systems | Nov-2013 | R | Tri-Annual Database Maintenance (TADM) completed | |
| Nov-2013 | S | UFGS 21 21 00.00 40 Carbon-Dioxide Fire Extinguishing Systems | Nov-2013 | R | Tri-Annual Database Maintenance (TADM) completed | |
| Nov-2013 | S | UFGS 22 05 83.63 Cured-In-Place Pipe (CIPP) Lining for Plumbing Applications | Nov-2013 | R | Tri-Annual Database Maintenance (TADM) completed | |
| Nov-2013 | S | UFGS 22 05 83.63 Cured-In-Place Pipe (CIPP) Lining for Plumbing Applications | Nov-2013 | R | Tri-Annual Database Maintenance (TADM) completed | |
| Nov-2013 | N | UFGS 23 64 10 Water Chillers, Vapor Compression Type | Aug-2008 | C | 1 | Added subparts 2.3 and 3.2; revised subparts 2.2.2.2, 2.4.1, 2.7.13. 2.7.16, 2.8.5, 2.17.5.1 and 3.5.2 |
| Nov-2013 | N | UFGS 23 64 26 Chilled, Chilled-Hot, and Condenser Water Piping Systems | Aug-2009 | C | 1 | Added subparts 2.3 and 3.2; revised subparts 2.2.2.2, 2.4.1, 2.7.13. 2.7.16, 2.8.5, 2.17.5.1 and 3.5.2 |
| Nov-2013 | N | UFGS 23 81 00.00 20 Unitary Air Conditioning Equipment | Nov-2009 | C | 1 | Revised subparts 2.2.1, 2.2.2, 2.3, 2.4, 2.4.1, 2.4.2, 2.5.1, 2.5.3, 2.8 and 3.2.4 |
| Nov-2013 | S | UFGS 26 05 13.00 10 Medium-Voltage Cables | Nov-2013 | R | Tri-Annual Database Maintenance (TADM) completed | |
| Nov-2013 | S | UFGS 26 05 13.00 10 Medium-Voltage Cables | Nov-2013 | R | Tri-Annual Database Maintenance (TADM) completed | |
| Nov-2013 | S | UFGS 26 12 19.00 40 Pad-Mounted, Liquid-Filled Medium-Voltage Transformers | Feb-2011 | C | 1 | Section 26 12 19.20 was replaced by 26 12 21 SINGLE-PHASED PAD- MOUNTED TRANSFORMERS within the General Note |
| Nov-2013 | N | UFGS 26 12 19.20 Single-Phase Pad-Mounted Transformers | Apr-2006 | D | Retired; Superseded by UFGS 26 12 21 Single-Phase Pad-Mounted Transformers. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Nov-2013 | N | UFGS 26 12 21 Single-Phase Pad-Mounted Transformers | Nov-2013 | N | Superseding UFGS 26 12 19.20 SINGLE-PHASE PAD-MOUNTED TRANSFORMERS | |
| Nov-2013 | N | UFGS 26 41 00 Lightning Protection System | Nov-2013 | N | Superseding UFGS 26 41 00.00 20 Lightning Protection System and UFGS 26 41 01.00 10 Lightning Protection System | |
| Nov-2013 | N | UFGS 26 41 00.00 20 Lightning Protection System | Apr-2006 | D | Superseded by UFGS 26 41 00 Lightning Protection System. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Nov-2013 | A | UFGS 26 41 01.00 10 Lightning Protection System | Nov-2008 | D | Superseded by UFGS 26 41 00 Lightning Protection System. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Nov-2013 | A | UFGS 26 41 01.00 10 Lightning Protection System | Nov-2008 | D | Superseded by UFGS 26 41 00 Lightning Protection System. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Nov-2013 | A | UFGS 26 41 01.00 10 Lightning Protection System | Nov-2008 | D | Superseded by UFGS 26 41 00 Lightning Protection System. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Nov-2013 | A | UFGS 26 41 01.00 10 Lightning Protection System | Nov-2008 | D | Superseded by UFGS 26 41 00 Lightning Protection System. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Nov-2013 | A | UFGS 27 15 19.00 10 Wire Line Data Transmission System | Apr-2006 | D | Superseded by UFGS 27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Nov-2013 | A | UFGS 27 21 10.00 10 Fiber Optic Data Transmission System | Jul-2006 | D | Superseded by UFGS 27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Nov-2013 | N | UFGS 31 23 00.00 20 Excavation and Fill | Feb-2011 | C | 1 | Revised subpart 1.6 and table in subpart 2.10 |
| Nov-2013 | N | UFGS 31 62 19 Timber Piles | Jan-2008 | C | 1 | Revised subpart 2.1.4 |
| Nov-2013 | N | UFGS 32 01 19.61 Sealing of Joints in Rigid Pavement | Apr-2006 | C | 1 | Revised notes before Part 1 and subparts 2.1.1 and 3.1.2.1. Deleted subparts 1.6.2.1 Hot-Poured Liquid Sealant and 2.1.1.2 Sealant, Joint, Jet- |
| Nov-2013 | N | UFGS 32 10 00 [Pervious] Bituminous Concrete Pavement | Aug-2008 | C | 1 | Revised subparts 2.5 and 3.3.2.1 |
| Nov-2013 | N | UFGS 32 12 17 Hot Mix Bituminous Pavement | Apr-2008 | C | 1 | Revised subparts 1.6.1, 2.2, 2.5.1, 2.5.2, 3.3, 3.5.2.2 and 3.5.2.3 |
| Nov-2013 | N | UFGS 32 13 13.06 Portland Cement Concrete Pavement for Roads and Site Facilities | Nov-2011 | C | 1 | Added subparts 1.2, 2.1.1.2, 2.1.1.4 and 2.1.2; Revised subparts 1.4, 1.6.2, 2.1.1, 2.1.3, 2.1.3.1, 2.3, 3.3.7, 3.7.5.1, 3.7.5.2 and 3.7.7 |
| Nov-2013 | N | UFGS 32 13 43 Pervious Concrete Paving | Nov-2011 | C | 1 | Revised subparts 1.3, 1.5.1 and 3.3.4 |