Below is a listing of the Revisions and Changes made to UFGS Sections for each release. You can narrow the list by selecting a UFGS Release date from the drop-down and clicking 'Apply'.
| KEY | PREPARING ACTIVITY (PA) | A Army | N Navy | F Air Force | S NASA [ARCHIVED] |
|---|---|---|---|---|---|
| ACTION | N New | R Revision | C Change | D Deletion |
| Release | PA | UFGS Section | Date | Action | Change # | Nature of Change or Revision |
|---|---|---|---|---|---|---|
| Nov-2013 | N | UFGS 33 05 23.19 Trenchless Excavation Using Microtunneling | Apr-2006 | C | 1 | Revised subparts 1.2, 1.3.1, 2.4 and 3.1.1 |
| Nov-2013 | N | UFGS 33 11 00 Water Utility Distribution Piping | Feb-2011 | C | 2 | Revised subparts 2.1.2.7, 2.2.2.17, 3.1.2.2 and 3.2.2 |
| Nov-2013 | N | UFGS 33 32 13.14 Packaged Sewage Lift Stations, Grinder Pump Type | Jan-2008 | C | 1 | Revised subpart 2.5.3 and 2.6.2.2 |
| Nov-2013 | N | UFGS 33 52 90.00 20 Welding for POL Service Piping | Feb-2010 | C | 1 | Revised subpart 3.3 |
| Nov-2013 | A | UFGS 33 82 33.00 10 Coaxial Cable Data Transmission System | Apr-2006 | D | Superseded by UFGS 27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Nov-2013 | N | UFGS 46 25 14 Coalescing [or Vertical Tube] Oil-Water Separators | Feb-2011 | C | 1 | Revised subpart 3.2 |
| Aug-2013 | A | UFGS 00 31 10 Metric Measurements | Apr-2006 | D | Section removed from UFGS Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Aug-2013 | N | UFGS 01 14 00 Work Restrictions | Nov-2011 | C | 1 | Tailoring and changes for NAVFAC NW throughout |
| Aug-2013 | A | UFGS 01 32 01.00 10 Project Schedule | Aug-2008 | C | 1 | Require use of Primavera P6 |
| Aug-2013 | N | UFGS 01 33 29.00 20 Sustainable Requirements | Aug-2013 | N | NEW; Interim change to 01 33 29, LEED DOCUMENTATION, to include the Guiding Principles, for Navy-use only. | |
| Aug-2013 | N | UFGS 01 35 26 Governmental Safety Requirements | Feb-2012 | C | 2 | Modified subparts 1.3,1.6.1, 3.1.3, 3.4; Removed "A" for accept from Submittal Items |
| Aug-2013 | N | UFGS 01 57 19.00 20 Temporary Environmental Controls | Nov-2011 | C | 1 | Modified throughout. Correctly classified Universal Waste and Asbestos material, removed tailoring from ECATTS paragraph, changed Environmental Management Plan to Environmental Protection Plan throughout and moved to Part 1. |
| Aug-2013 | N | UFGS 01 57 19.01 20 Supplemental Temporary Environmental Controls | Feb-2010 | C | 1 | Added requirements for NAVFAC NW, including Definitions and Part 3 paragraphs. |
| Aug-2013 | A | UFGS 01 62 35 Recycled / Recovered / Biobased Materials | May-2013 | C | 1 | Additional biobased materials language |
| Aug-2013 | N | UFGS 06 13 33 Pier Timberwork | Apr-2006 | C | 1 | Modified subpart 2.1.1.2 |
| Aug-2013 | N | UFGS 07 52 00 Modified Bituminous Membrane Roofing | May-2012 | C | 1 | Modified note before Part 1, subparts 1.2, 1.7.1, 1.9.1, 1.12, 2.1 efg |
| Aug-2013 | A | UFGS 07 84 00 Firestopping | May-2010 | C | 1 | Industry input |
| Aug-2013 | N | UFGS 09 97 13.27 High Performance Coating for Steel Structures | Feb-2010 | C | 1 | Modified notes before Part 1 and in subpart 3.6 |
| Aug-2013 | S | UFGS 21 13 00.00 40 Fire-Suppression Sprinkler Systems | Aug-2013 | R | Tri-Annual Database Maintenance (TADM) completed | |
| Aug-2013 | A | UFGS 21 30 00 Fire Pumps | Apr-2008 | C | 1 | CCR 1147, fuel piping specified by NFPA 20 |
| Aug-2013 | N | UFGS 26 13 01 Pad-Mounted Dead-Front Air Insulated Switchgear | Aug-2013 | N | NEW | |
| Aug-2013 | N | UFGS 26 27 29 Marina Electrical Work | Apr-2006 | C | 1 | Modified subparts 2.2.3.2, 2.4.1, 2.14.3 (note) and 2.14.4 (note) |
| Aug-2013 | N | UFGS 31 62 13.20 Precast/Prestressed Concrete Piles | Aug-2009 | C | 1 | Modified subparts 1.5 and 3.5 (notes) |
| Aug-2013 | N | UFGS 33 24 00.00 20 [Extraction] [Monitoring] Wells | Apr-2006 | C | 1 | Modified subparts 2.1.1, 2.2.2, 2.9 and 3.9 |
| Aug-2013 | N | UFGS 46 07 53.13 Packaged Wastewater Treatment Equipment, Aeration | Feb-2011 | C | 2 | Modified note before Part 1, subparts 1.4, 2.16, 2.6.1, 2.7.3.1 (d), 2.8.3.1 (b3), 2.8.3.2 (b3, d1), 2.8.3.3 (b3), 2.13.10, 2.16, 3.3.1.1, 3.3.5.9, 3.5.2, 3.7.2 3.7.2.3 |
| Aug-2013 | N | UFGS 46 23 00 Grit Removal and Handling Equipment | Feb-2011 | C | 1 | Modified subparts 2.1.4.3, 2.1.6.2, 2.1.7.4, 2.1.10.1(b), 2.3.5(d), 2.6 |
| May-2013 | A | UFGS 01 62 35 Recycled / Recovered / Biobased Materials | May-2013 | R | Revised Section Title from RECYCLED / RECOVERED MATERIALS. Also, added Biopreferred Fed | |
| May-2013 | N | UFGS 03 45 00 Precast Architectural Concrete | Nov-2011 | C | 1 | Modified note before Part 1; added SD-07; modifed SD-11; modified subpart 1.4, 1.6, 1.7, 1.8.1, 1.9 (formerly 1.10), 3.9 and 3.16.1; deleted subparts 1.8.1.1, 1.8.1.2 and 1.9 |
| May-2013 | N | UFGS 05 21 19 Open Web Steel Joist Framing | Jul-2007 | C | 1 | Modified subpart 2.2.1 |
| May-2013 | N | UFGS 05 21 23 Steel Joist Girder Framing | Jul-2007 | C | 1 | modified subpart 2.2.1 |
| May-2013 | N | UFGS 07 21 13 Board and Block Insulation | May-2011 | C | 1 | modified subpart 1.3 |
| May-2013 | N | UFGS 07 21 16 Mineral Fiber Blanket Insulation | Nov-2011 | C | 1 | Modified subpart 1.3 |
| May-2013 | N | UFGS 07 21 23 Loose Fill Thermal Insulation | May-2011 | C | 1 | Modified subpart 1.3 |
| May-2013 | N | UFGS 07 22 00 Roof and Deck Insulation | Aug-2011 | C | 1 | Modified subpart 1.4.3 |
| May-2013 | N | UFGS 07 42 63 Fabricated Wall Panel Assemblies | May-2011 | C | 1 | modified subpart 1.5.10 |
| May-2013 | N | UFGS 07 57 13 Sprayed Polyurethane Foam (SPF) Roofing | May-2011 | C | 1 | modified subpart 1.4.6 |
| May-2013 | N | UFGS 08 14 00 Wood Doors | Aug-2011 | C | 1 | Modified subpart1.3 |
| May-2013 | N | UFGS 08 36 13 Sectional Overhead Doors | Aug-2011 | C | 1 | Modified subparts 2.2, 2.3, 2.4.1, 2.4.1.1, 2.4.3, 2.5.1, 2.6.4, 2.7 |
| May-2013 | N | UFGS 09 23 00 Gypsum Plastering | Aug-2010 | C | 1 | modified subpart 1.3.2 |
| May-2013 | N | UFGS 09 26 00 Veneer Plaster | May-2011 | C | 1 | Modified subpart 1.4 |
| May-2013 | N | UFGS 09 29 00 Gypsum Board | May-2011 | C | 1 | Modified subpart 1.3 |
| May-2013 | N | UFGS 09 64 00 Portable (Demountable) Wood Flooring | Aug-2010 | C | 1 | modified subpart 1.3 |
| May-2013 | N | UFGS 09 64 66 Wood Athletic Flooring | Aug-2010 | C | 1 | modified subpart 1.3 |
| May-2013 | N | UFGS 09 90 00 Paints and Coatings | May-2011 | C | 1 | modified subpart 1.4.4 |
| May-2013 | N | UFGS 10 22 13 Wire Mesh Partitions | Aug-2010 | C | 1 | modified subpart 1.4 |
| May-2013 | N | UFGS 10 22 26.13 Accordion Folding Partitions | Aug-2010 | C | 1 | modified subpart 1.3.4 |
| May-2013 | N | UFGS 10 22 26.23 Coiling Partitions | Aug-2010 | C | 1 | modified subpart 1.4 |
| May-2013 | N | UFGS 12 22 00 Curtains and Drapes | Aug-2010 | C | 1 | modified subpart 1.5 |
| May-2013 | A | UFGS 14 21 23 Electric Traction Passenger Elevators | Feb-2009 | C | 1 | Updated references to sections and paragraphs of ASME A17.1/CSA B44 |
| May-2013 | N | UFGS 22 00 00 Plumbing, General Purpose | Nov-2011 | C | 1 | modified subpart 2.1 |
| May-2013 | A | UFGS 23 00 00 Air Supply, Distribution, Ventilation, and Exhaust Systems | Aug-2010 | C | 1 | Added the option for pneumatic or electric damper operator |
| May-2013 | N | UFGS 23 03 00.00 20 Basic Mechanical Materials and Methods | Aug-2010 | C | 1 | modified subpart 1.4.5.3 |
| May-2013 | N | UFGS 26 35 43 400-Hertz (HZ) Solid State Frequency Converter | May-2011 | C | 1 | modified subparts 2.1.1.11, 2.2 and 2.4.3 |
| May-2013 | A | UFGS 26 42 15.00 10 Cathodic Protection System (Steel Water Tanks) | Feb-2013 | C | 1 | Inserted NOTES on Impressed Current Anodes and Anode Installation |
| May-2013 | N | UFGS 26 56 00 Exterior Lighting | May-2013 | R | Major revision. Supersedes 26 56 00.00 20 | |
| May-2013 | N | UFGS 26 56 00.00 20 Exterior Lighting | Aug-2012 | D | Superseded by UFGS 26 56 00 Exterior Lighting, Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| May-2013 | A | UFGS 33 01 98 Slip Lining of Existing Piping for Levee Applications | May-2013 | N | New UFGS Section | |
| May-2013 | A | UFGS 33 40 00 Stormwater Utilities | Feb-2010 | C | 2 | Added requirements for use of Polypropylene (PP) Pipe |
| Feb-2013 | A | UFGS 03 44 00 Reinforced Autoclave Aerated Concrete Panels | Feb-2013 | N | New UFGS section | |
| Feb-2013 | A | UFGS 07 08 27.00 10 Building Air Barrier System Testing for Commissioning | Feb-2013 | N | Superseding UFGS 07 27 00.45 10 Building Air Barrier System | |
| Feb-2013 | A | UFGS 07 27 00.45 10 Building Air Barrier System | May-2012 | D | Superseded by UFGS 07 08 27.00 10 Building Air Barrier System Testing for Commissioning Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Feb-2013 | A | UFGS 07 27 00.45 10 Building Air Barrier System | May-2012 | D | Superseded by UFGS 07 08 27.00 10 Building Air Barrier System Testing for Commissioning Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Feb-2013 | A | UFGS 07 27 00.45 10 Building Air Barrier System | May-2012 | D | Superseded by UFGS 07 08 27.00 10 Building Air Barrier System Testing for Commissioning Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Feb-2013 | A | UFGS 07 27 00.45 10 Building Air Barrier System | May-2012 | D | Superseded by UFGS 07 08 27.00 10 Building Air Barrier System Testing for Commissioning Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Feb-2013 | A | UFGS 07 54 19 Polyvinyl Chloride Roofing | Feb-2013 | R | Title revision and complete update | |
| Feb-2013 | A | UFGS 09 65 00 Resilient Flooring | Aug-2010 | C | 1 | Adjusted sustainability requirements |
| Feb-2013 | A | UFGS 21 13 13.00 10 Wet Pipe Sprinkler System, Fire Protection | May-2009 | C | 1 | Removed disinfection requirements and galvanized steel piping components |
| Feb-2013 | A | UFGS 21 13 17.00 10 Dry Pipe Sprinkler System, Fire Protection | May-2009 | C | 1 | Removed disinfection requirements and galvanized steel piping components |
| Feb-2013 | A | UFGS 21 13 18.00 10 Preaction and Deluge Sprinkler Systems, Fire Protection | May-2009 | C | 1 | Removed disinfection requirements and galvanized steel piping components |
| Feb-2013 | A | UFGS 23 07 00 Thermal Insulation for Mechanical Systems | Feb-2013 | R | Revised vapor barrier and insulation requirements. | |
| Feb-2013 | A | UFGS 23 11 25 Facility Gas Piping | Nov-2008 | C | 1 | Added CSST, Gas Shut-off, Pressure Regulator, Bolting Gasket and Identification requirements |
| Feb-2013 | N | UFGS 23 81 47 Water-Loop and Ground-Loop Heat Pump Systems | Aug-2008 | C | 1 | Modified subpart 1.6 and notes before part 1 |
| Feb-2013 | A | UFGS 26 42 15.00 10 Cathodic Protection System (Steel Water Tanks) | Feb-2013 | R | Complete update. | |
| Feb-2013 | S | UFGS 26 51 00.00 40 Interior Lighting | Feb-2013 | R | Updated the entire section | |
| Feb-2013 | N | UFGS 33 51 15 Natural-Gas / Liquid Petroleum Gas Distribution Pipelines | Nov-2008 | C | 1 | Removed fiberglass piping, and added CSST and EFV |
| Feb-2013 | N | UFGS 46 07 53.13 Packaged Wastewater Treatment Equipment, Aeration | Feb-2011 | C | 1 | Modified subpart 2.7.3.1 |
| Feb-2013 | N | UFGS 46 43 21 Circular Clarifier Equipment | Feb-2011 | C | 2 | Modified subpart 2.2.3.2 |
| Dec-2012 | A | UFGS 23 07 00 Thermal Insulation for Mechanical Systems | Aug-2010 | C | 2 | INTERIM RELEASE: Removed polyisocyanurate insulation throughout the section. |
| Nov-2012 | S | UFGS 01 32 17.00 20 Cost-Loaded Network Analysis Schedules (NAS) | Aug-2010 | C | 1 | Modified subparts 1.4 and 1.4 to add Primavera P6 |
| Nov-2012 | S | UFGS 01 33 00 Submittal Procedures | May-2011 | C | 2 | In the last paragraph of the General Note, changed CONSTRUCTION to DESIGN-BID-BUILD within the Army tailoring tag |
| Nov-2012 | A | UFGS 01 45 35 Special Inspections | Aug-2008 | C | 1 | Section title change only; formerly SPECIAL INSPECTION FOR SEISMIC- RESISTING SYSTEMS |
| Nov-2012 | S | UFGS 01 91 00.00 40 Commissioning | Nov-2012 | N | New (for NASA Only) | |
| Nov-2012 | S | UFGS 03 62 16 Metallic Non-Shrink Grouting | Feb-2012 | C | 1 | There was an incomplete statement in Subpart 2.1, which has been corrected |
| Nov-2012 | A | UFGS 04 20 00 Unit Masonry | Feb-2011 | C | 1 | CCR: 2299: Added provisions for telescoping bar positioners |
| Nov-2012 | S | UFGS 05 14 00.13 Welding Structural Aluminum Framing | Nov-2010 | C | 2 | Updated CSI Section Format per latest UFC 1-300-02, - Added Subpart 1.3, deleted Subpart 1.4 |
| Nov-2012 | S | UFGS 05 52 00 Metal Railings | Feb-2011 | C | 2 | Imperative language |
| Nov-2012 | S | UFGS 07 41 63 Fabricated Roof Panel Assemblies | May-2009 | C | 1 | Tri-Annual Database Maintenance which includes, updating CSI Section Format per latest UFC 1-300-02; Submittal Article compliance, Imperative language and a few minor changes |
| Nov-2012 | S | UFGS 07 41 63 Fabricated Roof Panel Assemblies | May-2009 | C | 1 | Tri-Annual Database Maintenance (TADM) completed |
| Nov-2012 | A | UFGS 08 33 13 Coiling Counter Doors | May-2009 | C | 2 | CCR 1919: added test tags and warranty submittal |
| Nov-2012 | S | UFGS 08 33 23 Overhead Coiling Doors | Jul-2007 | C | 1 | Updated Section Format per latest UFC 1-300-02,removed text (redundant) text from Submittal Article and located info in body of the text in the appropriate Part; added testing tags at several locations. |
| Nov-2012 | A | UFGS 08 34 59 Vault Doors and Day Gates | Aug-2008 | C | 1 | Added Sustainability Requirements |
| Nov-2012 | S | UFGS 08 41 13 Aluminum-Framed Entrances and Storefronts | Feb-2011 | C | 1 | Tri-Annual Database Maintenance (TADM) completed |
| Nov-2012 | S | UFGS 08 41 13 Aluminum-Framed Entrances and Storefronts | Feb-2011 | C | 1 | Tri-Annual Database Maintenance which includes, updating CSI Section Format per latest UFC 1-300-02; Submittal Article compliance, Imperative language and a few minor changes. |
| Nov-2012 | S | UFGS 09 23 82 Fireproof Gypsum Plastering | May-2010 | C | 1 | Updated CSI Section Format per latest UFC 1-300-02; added Subpart 1.2,1.2.1 |
| Nov-2012 | A | UFGS 09 24 23 Cement Stucco | May-2009 | C | 1 | Added Sustainability Requirements |
| Nov-2012 | A | UFGS 09 62 38 Static-Control Flooring | Nov-2012 | N | Superseding UFGS 09 65 36 Static-Control Resilient Flooring. Section update with addition of static-control carpet | |
| Nov-2012 | A | UFGS 09 65 36 Static-Control Resilient Flooring | Nov-2010 | D | Superseded by UFGS 09 62 38 Static Control Flooring for conformance with current CSI MasterFormat. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives. |
|
| Nov-2012 | S | UFGS 09 67 23.13 Standard Resinous Flooring | Aug-2010 | C | 1 | Updated CSI Section Format per latest UFC 1-300-02; modified Submittal Article; modified titles in Subpart 3.2.4, 3.3.1, 3.3.2 and 3.3, other minor revisions |
| Nov-2012 | A | UFGS 09 72 00 Wallcoverings | Nov-2012 | R | Title change from Wall Coverings. Deleted duplicate product information, updated submittal requirements and incorporated sustainability updates | |
| Nov-2012 | A | UFGS 10 14 00.20 Interior Signage | Nov-2012 | N | Superseding UFGS 10 14 02 Interior Signage. Update of the entire section. |