Export to CSV

Below is a listing of the Revisions and Changes made to UFGS Sections for each release. You can narrow the list by selecting a UFGS Release date from the drop-down and clicking 'Apply'.

KEYPREPARING ACTIVITY (PA)A ArmyN NavyF Air ForceS NASA [ARCHIVED]
ACTIONN NewR RevisionC ChangeD Deletion
Release PA UFGS Section Action Change # Nature of Change or Revision
May-2021 N UFGS 26 27 14.00 20 Electricity Metering C 1 In response to the following: CCR 937, IEC 60687 has been removed from the Reference Article and the section text; CCR 4620, the accuracy class in potential and current transformers was changed to "0.15" in paragraphs Potential Transformer Requirements (2.1.2) item f. and Current Transformer Requirements (2.1.3) item b.; and CCR 5117, reference to a 'Voltage Requirements' paragraph was removed from paragraph (2.1.5) Disconnect Method, item c.
May-2021 N UFGS 26 27 29 Marina Electrical Work R Complete review and update.
May-2021 N UFGS 26 29 23 Adjustable Speed Drive (ASD) Systems Under 600 Volts C 1 Changes made to address various CCRs: added "IEC 61000-3-12" to References and paragraph Power Line Surge Protection (1.3.2.1); replaced reference UL 508C with "UL 61800-5-1"; ASD was changed to "110" percent in list item d. and "IEC" was added to list item r. in article (2.1) ADJUSTABLE SPEED DRIVES ; and article (2.2) ENCLOSURES was updated.
May-2021 A UFGS 26 42 13 Galvanic (Sacrificial) Anode Cathodic Protection (GACP) System N New unified section superseding UFGS 26 42 13.00 20 CATHODIC PROTECTION BY GALVANIC ANODES and UFGS 26 42 14.00 10 CATHODIC PROTECTION SYSTEM (SACRIFICIAL ANODE).
May-2021 N UFGS 26 42 13.00 20 Cathodic Protection by Galvanic Anodes D Superseded by new unified UFGS 26 42 13 GALVANIC (SACRIFICIAL) ANODE CATHODIC PROTECTION (GACP) SYSTEM
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
May-2021 A UFGS 26 42 14.00 10 Cathodic Protection System (Sacrificial Anode) D Superseded by UFGS 26 42 13 GALVANIC (SACRIFICIAL) ANODE CATHODIC PROTECTION (GACP) SYSTEM.
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
May-2021 A UFGS 26 42 15 Cathodic Protection System for the Interior of Steel Water Tanks N New unified section superseding UFGS 25 42 15.00 10 CATHODIC PROTECTION SYSTEM (STEEL WATER TANKS) and UFGS 26 42 22.00 20 CATHODIC PROTECTION SYSTEM FOR STEEL WATER TANKS.
May-2021 A UFGS 26 42 15.00 10 Cathodic Protection System (Steel Water Tanks) D Superseded by UFGS 26 42 15 CATHODIC PROTECTION SYSTEM FOR THE INTERIOR OF STEEL WATER TANKS.
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
May-2021 A UFGS 26 42 17 Impressed Current Cathodic Protection (ICCP) System N New unified section superseding UFGS 26 42 17.00 10 CATHODIC PROTECTION SYSTEM (IMPRESSED CURRENT) and UFGS 26 42 19.00 20 CATHODIC PROTECTION BY IMPRESSED CURRENT.
May-2021 A UFGS 26 42 17.00 10 Cathodic Protection System (Impressed Current) D Superseded by UFGS 26 42 17 IMPRESSED CURRENT CATHODIC PROTECTION (ICCP) SYSTEM.
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
May-2021 N UFGS 26 42 19.00 20 Cathodic Protection by Impressed Current D Superseded by new unified UFGS 26 42 17 IMPRESSED CURRENT CATHODIC PROTECTION (ICCP) SYSTEM
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
May-2021 N UFGS 26 42 22.00 20 Cathodic Protection System for Steel Water Tanks D Superseded by new unified UFGS 26 42 15 CATHODIC PROTECTION SYSTEM FOR THE INTERIOR OF STEEL WATER TANKS
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
May-2021 N UFGS 26 51 00 Interior Lighting C 1 Changes made to address various CCRs: added new paragraph (1.5.8) "Photometric Plan"; updated Specifier Note in LED Light Sources (2.3.1); updated (2.6.1.1) Exit Signs with Battery Backup and (2.6.6) Central Emergency Lighting System.
May-2021 A UFGS 32 13 15.20 Concrete Pavement for Fuel Storage Containment Dikes C 1 Added impermeable liner system requirements in response to CCR 7040.
May-2021 A UFGS 35 01 70.13 Wire Rope for Gate Operating Devices R Complete review and update.
May-2021 A UFGS 35 20 16.54 Slide Gates and Actuators N New UFGS.
May-2021 A UFGS 35 45 02.00 10 Submersible Pump, Axial-Flow and Mixed-Flow Type R Complete review and update.
May-2021 A UFGS 46 07 13.13 Precipitation/Coagulation/Flocculation (P/C/F) Water Treatment N Superseding UFGS 02 51 13 PRECIPITATION/COAGULATION/FLOCCULATION WATER TREATMENT.
May-2021 A UFGS 46 20 20 Sewage Bar Screen and Mechanical Shredder R Complete review and update.
May-2021 A UFGS 46 24 16 Comminutors R Complete review and update.
May-2021 A UFGS 46 51 00.00 10 Air and Gas Diffusion System R Complete review and update including section title change.
May-2021 A UFGS 46 53 62 Continuous Loop Reactor (CLR) Wastewater Treatment System R Complete review and update including section title change.
May-2021 A UFGS 46 61 00 Filtration Equipment R Complete review and update.
May-2021 A UFGS 46 66 56 Open-Channel Disinfection Equipment R Complete review and update.
Feb-2021 N UFGS 01 20 00 Price and Payment Procedures C 1 In response to CCR 9618, reference to FAR 32.503-6 has been replaced with "FAR 32.103 Progress payments under construction contracts" in paragraph (1.7.1) "Obligation of Government Payments" .
Feb-2021 N UFGS 01 31 23.13 20 Electronic Construction and Facility Support Contract Management System (eCMS) C 6 In response to CCRs 9429 and 9621, removed reference to DoD Manual 5200.01-V4 and all FOUO designations; replaced "FOUO - For Official Use Only" with "CUI Controlled Unclassified Information" throughout; and changed CLASS heading in Table 1 to "DESIG" (designation).
Feb-2021 S UFGS 01 33 00 Submittal Procedures C 4 Incorporation of the following CCRs: Incorporated PPI Information CCR# 7812 - Changed Title to Certification of Submittal in 1.17 CCR# 7894 - Updated paragraph 1.6.1 for non-Army projects CCR# 8991 - Added 23 09 00 to paragraph 1.5.2 CCR# 9026 - Deleted the 2nd sentence in par 1.10.2. Added “For variations that include design changes or some material or product substitutions, the Government may require an evaluation and analysis by a licensed professional engineer hired by the contractor. in para 1.10.1 CCR# 9065 - Deleted Tailoring Notes for 1.4.2.1, 1.4.2.2, 1.4.2.3 and 1.4.2.4. Added note to 1.4.2 CCR# 9073 - Added Section 01 91 00.15 20: Commissioning Plan, Certificate of Readiness, and Commissioning Report" to paragraph 1.5.2 CCR# 9326
Feb-2021 A UFGS 01 33 23.33 Aviation Fuel System Specific Submittal Requirements C 1 Deleted redundant drawing sizes from paragraph 1.1.1 in response to CCR 8754 and updated paragraph 2.1.1 in response to CCR 8756.
Feb-2021 N UFGS 01 33 29 Sustainability Requirements and Reporting R Revised to align with industry standards; to align with UFC 1-200-02 revision; to combine DB and DBB requirements into a Tri-Service, tailorable spec; and reorganized paragraphs into hierarchical presentation. Titled changed from "SUSTAINABILITY REPORTING" to "SUSTAINABILITY REQUIREMENTS AND REPORTING"
Feb-2021 N UFGS 01 45 00.00 20 Quality Control C 8 In response to the following CCRs: 8956 - add reference to UFGS Section 01 32 16.00 20; and 9339 - coordinate commissioning and sustainability with UFGS Sections 01 91 00.15 20 and UFGS 01 33 29.
Feb-2021 N UFGS 01 45 00.00 20 Quality Control C 8 In response to the following CCRs: CCR 8960, the Note pertaining to paragraph "Registered Fire Protection Engineer" (1.5.8) has been revised for clarity; CCR 8961, paragraph "QC Administrative Assistant" (1.5.10) has been removed to align with the other QC sections; CCR 8827, changes to submittal requirements for NAVFAC PAC to mitigate schedule impacts: revised Submittal Article SD-01 and paragraph "CONSTRUCTION INDOOR AIR QUALITY (IAQ) MANAGEMENT PLAN" (1.17).
Feb-2021 N UFGS 01 45 00.10 20 Quality Control for Minor Construction C 3 In response to CCR 8942, "KO" has been replaced with "Contracting Officer" throughout, "Pre-Construction Conference" and "Pre-Construction Meeting" have been tailored for Army and Navy respectively, and various clerical tagging corrections have been made.
Feb-2021 A UFGS 01 78 23.33 Operation and Maintenance Manuals for Aviation Fuel Systems C 1 Deleted editing note in paragraph 2.1.2, corrected formatting issues in paragraph 2.2, and updated editing note in paragraph 3.3.6 in response to CCR 8929.
Feb-2021 N UFGS 01 91 00.15 20 Total Building Commissioning N Navy-only Commissioning Section superseding UFGS-01 91 00.15 TOTAL BUILDING COMMISSIONING.
Feb-2021 N UFGS 01 91 00.15 Building Commissioning D Superseded by UFGS-01 91 00.15 20 TOTAL BUILDING COMMISSIONING
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Feb-2021 A UFGS 02 32 00 Subsurface Drilling, Sampling, and Testing D Superseded by UFGS 02 32 13 SUBSURFACE DRILLING AND SAMPLING without revision to comply with MF 2011 in response to CCR 1924.
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Feb-2021 A UFGS 02 32 13 Subsurface Drilling and Sampling N Superseding UFGS 02 32 00 SUBSURFACE DRILLING, SAMPLING, AND TESTING without revision to comply with MF 2011 in response to CCR 1924. Nontechnical number and title change.
Feb-2021 A UFGS 02 35 27 Soil-Bentonite (S-B) Slurry Trench D Superseded by UFGS 31 56 13.13 SOIL-BENTONITE SLURRY WALLS without revision to comply with MF 2011 in response to CCR 1925.
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Feb-2021 A UFGS 02 51 19 Solidification and Stabilization Decontamination N Superseding UFGS 02 55 00 SOLIDIFICATION/STABILIZATION (S/S) OF CONTAMINATED MATERIAL without revision to comply with MF 2011 in response to CCR 1934. Nontechnical number and title change.
Feb-2021 A UFGS 02 53 16 Remediation of Contaminated Soils By Thermal Desorption D Superseded by UFGS 02 53 16.13 REMEDIATION OF CONTAMINATED SOILS BY THERMAL DESORPTION without revision to comply with MF 2011 in response to CCR 1931. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Feb-2021 A UFGS 02 53 16.13 Remediation of Contaminated Soils by Thermal Desorption N Superseding UFGS 02 53 16 REMEDIATION OF CONTAMINATED SOILS BY THERMAL DESORPTION without revision to comply with MF 2011 in response to CCR 1931. Nontechnical number change.
Feb-2021 A UFGS 02 54 19.13 Bioremediation Using Landfarming N Superseding UFGS 02 54 20 BIOREMEDIATION OF SOILS USING LANDFARMING SYSTEMS without revision to comply with MF 2011 in response to CCR 1932. Nontechnical number and title change.
Feb-2021 A UFGS 02 54 19.16 Bioremediation of Soils Using Windrow Composting N Superseding UFGS 02 54 21 BIOREMEDIATION OF SOILS USING WINDROW COMPOSTING without revision to comply with MF 2011 in response to CCR 1933. Nontechnical number change.
Feb-2021 A UFGS 02 54 20 Bioremediation of Soils Using Landfarming Systems D Superseded by UFGS 02 54 19.13 BIOREMEDIATION USING LANDFARMING without revision to comply with MF 2011 in response to CCR 1932.
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Feb-2021 A UFGS 02 54 21 Bioremediation of Soils Using Windrow Composting D Superseded by UFGS 02 54 19.16 BIOREMEDIATION OF SOILS USING WINDROW COMPOSTING without revision to comply with MF 2011 in response to CCR 1933.
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Feb-2021 A UFGS 02 55 00 Solidification/Stabilization (S/S) of Contaminated Material D Superseded by UFGS 02 51 19 SOLIDIFICATION AND STABILIZATION DECONTAMINATION without revision to comply with MF 2011 in response to CCR 1934.
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Feb-2021 A UFGS 02 56 13 Waste Containment Geomembrane D Superseded by UFGS 02 56 13.13 GEOMEMBRANE WASTE CONTAINMENT without revision to comply with MF 2011 in response to CCR 1935.
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Feb-2021 A UFGS 02 56 13.13 Geomembrane Waste Containment N Superseding UFGS 02 56 13 WASTE CONTAINMENT GEOMEMBRANE without revision to comply with MF 2011 in response to CCR 1935. Nontechnical number and title change.
Feb-2021 A UFGS 02 56 13.16 Clay Waste Containment N Superseding UFGS 02 56 14 CLAY BARRIER LAYER without revision to comply with MF 2011 in response to CCR 1936. Nontechnical number and title change.
Feb-2021 A UFGS 02 56 13.19 Geosynthetic Clay Liner Waste Containment N Superseding UFGS 02 56 15 GEOSYNTHETIC CLAY LINER (GCL) without revision to comply with MF 2011 in response to CCR 1937. Nontechnical number and title change.
Feb-2021 A UFGS 02 56 14 Clay Barrier Layer D Superseded by UFGS 02 56 13.16 CLAY WASTE CONTAINMENT without revision to comply with MF 2011 in response to CCR 1936.
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Feb-2021 A UFGS 02 56 15 Geosynthetic Clay Liner (GCL) D Superseded by UFGS 02 56 13.19 GEOSYNTHETIC CLAY LINER WASTE CONTAINMENT without revision to comply with MF 2011 in response to CCR 1937. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Feb-2021 A UFGS 02 61 13 Excavation and Handling of Contaminated Material C 1 Deleted and updated references in response to CCRs 2245 and 4992. Updated submittals in response to CCR 6032.
Feb-2021 A UFGS 02 66 00 Select Fill and Topsoil for Landfill Cover D Superseded by UFGS 02 66 13 SELECT FILL AND TOPSOIL FOR LANDFILL COVER without revision to comply with MF 2011 in response to CCR 1939.
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Feb-2021 A UFGS 02 66 10 Test Fill D Superseded by UFGS 02 66 16 TEST FILL without revision to comply with MF 2011 in response to CCR 1940.
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Feb-2021 A UFGS 02 66 13 Select Fill and Topsoil for Landfill Cover N Superseding UFGS 02 66 00 SELECT FILL AND TOPSOIL FOR LANDFILL COVER without revision to comply with MF 2011 in response to CCR 1939. Nontechnical number change.
Feb-2021 A UFGS 02 66 16 Test Fill N Superseding UFGS 02 66 10 TEST FILL without revision to comply with MF 2011 in response to CCR 1940. Nontechnical number change.
Feb-2021 N UFGS 03 30 00 Cast-In-Place Concrete C 1 In response to CCR 6876, the mark for ASTM A615/A615M reinforcing bars was changed from "A" to "S" in paragraph (2.6.1) Reinforcing Bars, list item "b".
Feb-2021 N UFGS 03 45 00 Precast Architectural Concrete C 1 In response to CCR 9837, reference to A, B and C grades were removed from the paragraph "Grout" (2.2.13).
Feb-2021 N UFGS 05 05 20 Post-Installed Concrete and Masonry Anchors N UFGS 05 05 20.00 27 added - New Section to address the requirements for post-installed concrete and masonry anchors.
Feb-2021 N UFGS 05 05 20.00 27 Post-Installed Concrete and Masonry Anchors N New section to address the requirements for post-installed concrete and masonry anchors.
Feb-2021 N UFGS 07 41 13 Metal Roof Panels C 4 In response to CCR 9492, updated paragraph (3.13) WARRANTY by removing "USACE" from the title and requirements for future contracts and arbitration.
Feb-2021 A UFGS 07 54 19 Polyvinyl Chloride Roofing C 3 Updated NRCA reference in response to CCR 9568.
Feb-2021 S UFGS 08 34 73 Sound Control Door Assemblies C 1 Added STC rating to Para 1.3.1.4 - CCR# 8318
Feb-2021 N UFGS 08 71 63.10 Electrical Locking Control for Brigs R Complete review of section.
Feb-2021 N UFGS 09 67 23.15 Fuel Resistive Resinous Flooring, 3-Coat System R Complete review and update.
Feb-2021 N UFGS 09 67 23.16 Fuel Resistive Resinous Flooring, 5-Coat System R Complete review and update.
Feb-2021 N UFGS 09 90 00 Paints and Coatings R Complete review and update.
Feb-2021 N UFGS 09 97 13.27 High Performance Coating for Steel Structures R Revised in response to the following: CCR 9541- title has been changed from "EXTERIOR COATING OF STEEL STRUCTURES" to "HIGH PERFORMANCE COATING FOR STEEL STRUCTURES"; CCR 9540 – 2.2 COATING SYSTEM – to allow 100% shop coating; CCR 9542 – SSPC requirements confirmed; and CCR # 9543 – Added notes to designer to carefully coordinate Division 05 and Division 08 UFGS when used. Indicated that this UFGS is required for coating of components indicated in UFC 4-211-01.
Feb-2021 N UFGS 13 34 19 Metal Building Systems C 1 In response to CCR 9491, updated paragraph (3.14) WARRANTY by removing Army tailoring and Specifier Note as well as requirements for future contracts and arbitration.
Feb-2021 A UFGS 21 13 25 High-Expansion Foam System, Fire Protection C 1 Updated Flanges and Gaskets paragraph in response to CCR 7781. Corrected formatting issues in response to CCR 8444. Updated paragraph 2.3.9 in response to CCR 9292.
Feb-2021 N UFGS 23 08 00.00 20 Commissioning of Mechanical[ and Plumbing] Systems N Reinstate Section Number 23 08 00.00 20. New Navy-only section covering commissioning requirements for HVAC and plumbing systems. This new section does not replace or supersede the section dated 08/08 which covered the requirements for testing, adjusting, and balancing (TAB) of HVAC air and water distribution systems. UFGS-23 08 00.00 20 (08/08) was superseded by UFGS-23 05 93.
Feb-2021 A UFGS 23 81 00 Decentralized Unitary HVAC Equipment C 1 Deleted contents of paragraph 2.3.4 and added note.
Feb-2021 N UFGS 26 27 14.00 20 Electricity Metering R Complete review and update.
Feb-2021 A UFGS 31 00 00 Earthwork C 2 Updated paragraph 1.5.4 in response to CCR 5210. Updated reference in response to CCR 7275. Updated paragraphs in Part 3 in response to CCRs 9380, 9381, 9382 and 9384.
Feb-2021 A UFGS 31 05 19 Geotextile D Superseded by UFGS 31 32 19.16 GEOTEXTILE SOIL STABILIZATION without revision to comply with MF 2011 in response to CCR 2079.
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Feb-2021 A UFGS 31 05 19.13 Geotextiles for Earthwork N Superseding UFGS 31 05 22 GEOTEXTILES USED AS FILTERS without revision to comply with MF 2011 in response to CCR 2082. Nontechnical number and title change.
Feb-2021 A UFGS 31 05 20 Geosynthetic Drainage Layer D Superseded by UFGS 31 32 19.13 GEOGRID SOIL STABILIZATION without revision to comply with MF 2011 in response to CCR 2080.
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Feb-2021 A UFGS 31 05 21 Geogrid Soil Reinforcement D Superseded by UFGS 31 35 19.13 GEOGRID SLOPE PROTECTION without revision to comply with MF 2011 in response to CCR 2081.
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Feb-2021 A UFGS 31 05 22 Geotextiles Used as Filters D Superseded by UFGS 31 05 19.13 GEOTEXTILES FOR EARTHWORK without revision to comply with MF 2011 in response to CCR 2082.
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Feb-2021 A UFGS 31 10 00 Site Clearing R Superseding UFGS 31 10 00 CLEARING FOR CIVIL WORKS without revision to comply with MF 2011 in response to CCR 2083. Nontechnical section title change.
Feb-2021 A UFGS 31 21 00 Off-Gassing Mitigation R Superseding UFGS 31 21 00 PIPING; OFF-GAS without revision to comply with MF 2011 in response to CCR 2086. Nontechnical title change.
Feb-2021 A UFGS 31 23 01 Underwater Blasting N New UFGS.
Feb-2021 A UFGS 31 23 06.00 Blasting - Surface N New UFGS.
Feb-2021 A UFGS 31 32 19.13 Geogrid Soil Stabilization N Superseding UFGS 31 05 20 GEOSYNTHETIC DRAINAGE LAYER without revision to comply with MF 2011 in response to CCR 2080. Nontechnical number and title change.
Feb-2021 A UFGS 31 32 19.16 Geotextile Soil Stabilization N Superseding UFGS 31 05 19 GEOTEXTILE without revision to comply with MF 2011 in response to CCR 2079. Nontechnical number and title change.
Feb-2021 A UFGS 31 32 23 Foundation Drilling and Grouting D Superseded by UFGS 31 43 13.13 CONCRETE PRESSURE GROUTING without revision to comply with MF 2011 in response to CCR 2090.
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Feb-2021 A UFGS 31 35 19.13 Geogrid Slope Protection N Superseding UFGS 31 05 21 GEOGRID SOIL REINFORCEMENT without revision to comply with MF 2011 in response to CCR 2081. Nontechnical number and title change.
Feb-2021 A UFGS 31 36 00 Gabions R Superseding UFGS 31 36 00 WIRE MESH GABIONS[ AND MATTRESSES] without revision to comply with MF 2011 in response to CCR 2091. Nontechnical title change.
Feb-2021 A UFGS 31 43 13.13 Concrete Pressure Grouting N Superseding UFGS 31 32 23 FOUNDATION DRILLING AND GROUTING without revision to comply with MF 2011 in response to CCR 2090. Nontechnical number and title change.
Feb-2021 A UFGS 31 56 13.13 Soil-Bentonite Slurry Walls N Superseding UFGS 02 35 27 SOIL-BENTONITE (S-B) SLURRY TRENCH without revision to comply with MF 2011 in response to CCR 1925. Nontechnical number and title change.
Feb-2021 A UFGS 31 60 00 Foundation Preparation D Superseded by UFGS 31 66 10 ROCK FOUNDATION PREPARATION without revision to comply with MF 2011 in response to CCR 2093.
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Feb-2021 A UFGS 31 62 23.13 Concrete-Filled Steel Piles R Superseding UFGS 31 62 23.13 CAST-IN-PLACE CONCRETE PILES, STEEL CASING without revision to comply with MF 2011 in response to CCR 2095. Nontechnical title change.
Feb-2021 A UFGS 31 66 10 Rock Foundation Preparation N Superseding UFGS 31 60 00 FOUNDATION PREPARATION without revision to comply with MF 2011 in response to CCR 2093. Nontechnical number and title change.
Feb-2021 A UFGS 31 73 00 Tunnel and Shaft Grouting D Superseded by UFGS 31 73 19 TUNNEL AND SHAFT GROUTING without revision to comply with MF 2011 in response to CCR 2097.
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Feb-2021 A UFGS 31 73 19 Tunnel and Shaft Grouting N Superseding UFGS 31 73 00 TUNNEL AND SHAFT GROUTING without revision to comply with MF 2011 in response to CCR 2097. Nontechnical number change.
Feb-2021 A UFGS 32 84 23 Underground Sprinklers R Superseding UFGS 32 84 23 UNDERGROUND SPRINKLER SYSTEMS without revision to comply with MF 2011 in response to CCR 2136. Nontechnical title change.
Feb-2021 N UFGS 33 01 50.55 Cleaning of Petroleum Storage Tanks R Replacing without change UFGS-33 01 50.60 / Non-technical Section Number change
Feb-2021 N UFGS 33 01 50.65 Inspection of Field Fabricated Fuel Storage Tanks N New section to address the requirements for an out of service Inspection of a Field Fabricated Fuel Storage Tank.
Feb-2021 A UFGS 33 09 53 Aviation Fuel Pump Control and Annunciation System (Type III) R Superseding UFGS 33 09 53 AVIATION FUEL PUMP CONTROL AND ANNUNCIATION SYSTEM without revision to comply with MF 2011 in response to CCR 2138. Nontechnical title change.