Spec. Division
01 - General Requirements
CCR
Summary

The Related Materials are available in various file formats in compressed ZIP  files.

History: Below is a listing of the Revisions and Changes made to this UFGS.

KEYPREPARING ACTIVITY (PA)A ArmyN NavyF Air ForceS NASA [ARCHIVED]
ACTIONN NewR RevisionC ChangeD Deletion
Release PA Action Change # Nature of Change or Revision
Nov-2023 N C 2 In response to CCR 13595, moved language related to warranty period requirements from PROJECT SCHEDULE paragraph (1.8) to CONSTRUCTION PHASE COMMISSIONING PLANS paragraph (3.7); added language for Air Force usage.
Aug-2023 N C 1 Clarified the language in COMMISSIONING FIRM paragraph (1.11)
May-2023 N N Section number has been reinstated with the unification of Army and Navy Commissioning Sections. This new version supersedes UFGS-01 91 00.15 10 and UFGS-01 91 00.15 20 TOTAL BUILDING COMMISSIONING. Title has been changed to BUILDING COMMISSIONING.
Feb-2021 N D Superseded by UFGS-01 91 00.15 20 TOTAL BUILDING COMMISSIONING Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
May-2020 N C 1 Preparing Activity changed to NAVFAC as this section has been for Navy-use only since 05-2019; In response to the following: CCR 6881, paragraph Project Schedule (1.6.2) is not appropriate for use on Navy projects and was removed; and CCR 8403, in paragraph Lead Commissioning Specialist (1.8.1) , "ASHRAE Commissioning Process Management Professional (CPMP) was changed to "ASHRAE Building Commissioning Professional (BCxP)"
Feb-2019 A R Complete review and update.
Aug-2018 A C 3 Sustainability updates required to coordinate with the Federal Codes and DoD policies and procedures.
Aug-2017 A C 2 Updated to coordinate archiving of Navy Section 23 09 23.13 20 BACnet Direct Digital Control Systems for HVAC to meet the requirement of 10 USC 2867 to adopt a "Department-wide, Open Protocol, Energy Monitoring and Utility Control System Specification" for use in Military construction and military family housing activity.
Feb-2017 A C 1 In response to CCR 5173, added two "S" submittals in SD-11.
May-2016 A N Superseding UFGS 23 08 00.00 10 COMMISSIONING OF HVAC SYSTEMS; Total Building Commissioning requirements for new construction and major renovations.