Feb-2010 N UFGS 33 61 14 Exterior Buried Preinsulated Water Piping R Section References (SRF) update
Feb-2010 N UFGS 34 43 00.00 20 Airfield Lighting R Section References (SRF) update
Feb-2010 N UFGS 35 59 13.14 20 Polymeric Piles R Section References (SRF) update
Dec-2009 N UFGS 01 32 17.00 20 Cost-Loaded Network Analysis Schedules (NAS) R INTERIM RELEASE: Section revised
Dec-2009 S UFGS 06 82 14 Fiberglass Reinforced Plastic (FRP) Pipe and Tube Railings R INTERIM RELEASE: Updated Criteria
Dec-2009 A UFGS 23 09 23 LonWorks Direct Digital Control for HVAC and Other Building Control Systems R INTERIM RELEASE: Restored to version prior to Nov-08 release
Dec-2009 A UFGS 25 10 10 Utility Monitoring and Control System (UMCS) Front End and Integration R INTERIM RELEASE: Restored to version prior to Nov-08 release
Nov-2009 N UFGS 01 30 00 Administrative Requirements R Deleted paragraph 1.15
Nov-2009 N UFGS 01 32 16.00 20 Small Project Construction Progress Schedules R Major revision
Nov-2009 N UFGS 01 32 17.00 20 Cost-Loaded Network Analysis Schedules (NAS) R Major revision
Nov-2009 N UFGS 01 45 02 NAVFAC Quality Control R Revised paragraph 1.7
Nov-2009 A UFGS 03 01 30 Restoration of Concrete in Historic Structures R Compliance with CSI SectionFormat
Nov-2009 A UFGS 03 01 32 Concrete Rehabilitation for Civil Works R Extensive reformat for conformance with CSI SectionFormat
Nov-2009 A UFGS 03 15 13.00 10 Expansion Joints, Contraction Joints, and Waterstops R Compliance with CSI SectionFormat
Nov-2009 A UFGS 03 15 14.00 10 Expansion Contraction and Construction Joints in Concrete for Civil Works R Compliance with CSI SectionFormat
Nov-2009 A UFGS 03 20 02 Steel Bars and Welded Wire Fabric for Concrete Reinforcement for Civil Works R Compliance with CSI SectionFormat
Nov-2009 A UFGS 03 23 00 Stressed Tendon Reinforcing R Compliance with CSI SectionFormat
Nov-2009 A UFGS 03 31 00.00 10 Cast-in-Place Structural Concrete R Compliance with CSI SectionFormat
Nov-2009 A UFGS 03 31 01.00 10 Cast-In-Place Structural Concrete for Civil Works R Compliance with CSI SectionFormat
Nov-2009 N UFGS 03 31 29 Marine Concrete with Service Life Modeling R Corrected table under subpart 2.1.2e
Nov-2009 A UFGS 03 33 00 Cast-In-Place Architectural Concrete R Compliance with CSI SectionFormat
Nov-2009 A UFGS 03 37 00 Preplaced-Aggregate Concrete R Compliance with CSI SectionFormat
Nov-2009 A UFGS 03 37 13 Shotcrete R Compliance with CSI SectionFormat
Nov-2009 A UFGS 03 37 23 Roller-Compacted Concrete for Mass Concrete Construction R Compliance with CSI SectionFormat
Nov-2009 A UFGS 03 37 29 Concrete for Concrete Cutoff Walls R Compliance with CSI SectionFormat
Nov-2009 A UFGS 04 01 40 Restoration and Cleaning of Masonry in Historic Structures R Extensive reformat for conformance with CSI SectionFormat
Nov-2009 A UFGS 04 21 26 Glazed Structural Clay Tile and Prefaced Concrete Masonry R Compliance with CSI SectionFormat
Nov-2009 A UFGS 04 23 00 Glass Unit Masonry R Compliance with CSI SectionFormat
Nov-2009 N UFGS 06 10 00 Rough Carpentry R Modified AWPA publication reference designations and other minor changes
Nov-2009 S UFGS 08 34 73 Sound Control Door Assemblies R Major maintenance
Nov-2009 A UFGS 09 97 02 Painting: Hydraulic Structures R Updated paint systems
Nov-2009 N UFGS 21 13 19.00 20 [Deluge] [Preaction] Fire Sprinkler Systems R Removed paragraph 1.2.1 regarding Y2K
Nov-2009 N UFGS 21 13 20.00 20 Foam Fire Extinguishing for Aircraft Hangars R Removed paragraph 1.2 regarding Y2K; Section References (SRF) update
Nov-2009 N UFGS 21 13 21.00 20 Foam Fire Extinguishing for Fuel Tank Protection R Removed paragraph 1.2 regarding Y2K; Section References (SRF) update
Nov-2009 N UFGS 21 13 22.00 20 Foam Fire Extinguishing for Haz/Flam Material Facility R Removed paragraph 1.2 regarding Y2K
Nov-2009 N UFGS 21 21 01.00 20 Carbon Dioxide Fire Extinguishing (High Pressure) R Removed paragraph 1.2 regarding Y2K
Nov-2009 N UFGS 21 21 02.00 20 Carbon Dioxide Fire Extinguishing (Low Pressure) R Removed paragraph 1.2 regarding Y2K
Nov-2009 N UFGS 21 22 00.00 20 Halon 1301 Fire Extinguishing R Removed paragraph 1.2 regarding Y2K
Nov-2009 N UFGS 22 00 00 Plumbing, General Purpose R Removed 1st 2 items under SD-03 Product Data and paragraph 1.10; other minor changes
Nov-2009 N UFGS 22 15 19.13 20 Large Nonlubricated Reciprocating Air Compressors (Over 300 HP) R Removed paragraph 1.3 regarding Y2K
Nov-2009 N UFGS 22 15 19.19 20 Nonlubricated Rotary Screw Air Compressors (100 HP and Larger) R Removed paragraph 1.3 regarding Y2K
Nov-2009 N UFGS 22 16 19.26 20 Large Centrifugal Air Compressors (Over 200 HP) R Removed paragraph 1.2 regarding Y2K
Nov-2009 A UFGS 23 00 00 Air Supply, Distribution, Ventilation, and Exhaust Systems R Revised Duct Test Holes and Cleaning and Adjusting in response to CCR's
Nov-2009 A UFGS 23 07 00 Thermal Insulation for Mechanical Systems R Revised firestopping to close a CCR
Nov-2009 N UFGS 23 22 26.00 20 Steam System and Terminal Units R Removed paragraph 1.2.4.5 regarding Y2K
Nov-2009 N UFGS 23 81 00.00 20 Unitary Air Conditioning Equipment R Removed paragraph 1.2 regarding Y2K; Section References (SRF) update
Nov-2009 N UFGS 26 12 19 Pad-Mounted, Liquid-Filled, Medium Voltage Transformers R Major revision
Nov-2009 N UFGS 28 31 02.00 20 Fire Alarm Reporting Systems - Digital Communicators R Removed paragraph 1.4 regarding Y2K
Nov-2009 A UFGS 32 11 29 Lime-[Stabilized] [Modified] Subgrade R Revisions throughout including, but not limited to, Pneumatic-Tired Rollers, Submittals, Mix Design, Installation, Sampling and Testing, Field Quality Control
Nov-2009 A UFGS 32 13 11 Concrete Pavement for Airfields and Other Heavy-Duty Pavements R Revisions throughout including, but not limited to, Test Section, Portland Cement, aggregate blending, other finishing equipment and broom finish
Nov-2009 A UFGS 32 13 11 Concrete Pavement for Airfields and Other Heavy-Duty Pavements R Revised throughout
Nov-2009 N UFGS 32 84 24 Irrigation Sprinkler Systems R Removed paragraph 1.2 regarding Y2K and paragraph 1.9
Nov-2009 N UFGS 33 11 00 Water Utility Distribution Piping R Section References (SRF) update
Nov-2009 N UFGS 33 11 23 Natural Gas and Liquid Petroleum Piping R Removed paragraph 1.2 regarding Y2K, removed Y2K info from SD-07 Certificates and paragraphs 1.7 and 2.1 including note in between
Nov-2009 N UFGS 33 52 43.00 20 Aviation Fuel Distribution and Dispensing R Removed paragraph 1.2.1 regarding Y2K
Nov-2009 N UFGS 44 42 13.00 20 Aeration Equipment R Removed paragraph 1.2 regarding Y2K; Section References (SRF) update
Nov-2009 N UFGS 44 42 23 Circular Clarifier R Removed paragraph 1.2 regarding Y2K, SD-07 Certificates, and paragraph 1.8
Nov-2009 N UFGS 44 42 39 Grit Collecting Equipment R Removed paragraph 1.3 regarding Y2K and SD-07 Certificates
Aug-2009 N INACTIVE-UFGS 09 97 13.15 Low VOC Polysulfide Interior Coating of Welded Steel Petroleum Fuel Tanks R Section References (SRF) update
Aug-2009 N UFGS 01 20 00.00 20 Price and Payment Procedures R Updated the last criteria NOTE (Costloaded NAS) in the introduction; updated paras 1.3, 1.5,1.6, 1.7.2.
Aug-2009 N UFGS 01 35 26 Governmental Safety Requirements R Major revision
Aug-2009 N UFGS 01 35 26 Governmental Safety Requirements R Major revision
Aug-2009 A UFGS 01 50 00 Temporary Construction Facilities and Controls R Revised USACE Project Sign requirements
Aug-2009 N UFGS 01 58 00 Project Identification R Minor revisions
Aug-2009 N UFGS 03 31 29 Marine Concrete with Service Life Modeling R Major revision
Aug-2009 A UFGS 05 21 13 Deep Longspan Steel Joist Framing R Extensive reformat for conformance with CSI SectionFormat
Aug-2009 A UFGS 05 21 16 Longspan Steel Joist Framing R Extensive reformat for conformance with CSI SectionFormat
Aug-2009 A UFGS 05 59 13 Fabrication of Hydraulic Steel Structures N New section
Aug-2009 A UFGS 06 41 16.00 10 Plastic-Laminate-Clad Architectural Cabinets R Compliance with CSI SectionFormat
Aug-2009 A UFGS 06 61 16 Solid Surfacing Fabrications R Compliance with CSI SectionFormat
Aug-2009 A UFGS 07 31 26 Slate Shingles R Compliance with CSI SectionFormat
Aug-2009 A UFGS 07 55 00 Protected Membrane Roofing (PMR) R Compliance with CSI SectionFormat
Aug-2009 N UFGS 07 57 13 Sprayed Polyurethane Foam (SPF) Roofing R Minor revisions
Aug-2009 A UFGS 07 61 01 Copper Roof System R Compliance with CSI SectionFormat
Aug-2009 A UFGS 07 62 10 Copper Sheet Metal Flashing R Compliance with CSI SectionFormat
Aug-2009 A UFGS 07 72 00 Roof Ventilators, Gravity-Type R Compliance with CSI SectionFormat
Aug-2009 A UFGS 08 34 01 Forced Entry Resistant Components R Compliance with CSI SectionFormat
Aug-2009 A UFGS 08 34 02 Bullet-Resistant Components R Compliance with CSI SectionFormat
Aug-2009 A UFGS 08 39 54 Blast Resistant Doors R Compliance with CSI SectionFormat
Aug-2009 N UFGS 08 51 13 Aluminum Windows R Major revision
Aug-2009 A UFGS 08 52 70 Wood Windows - Repair and Rehabilitation R Compliance with CSI SectionFormat
Aug-2009 A UFGS 08 62 00 Skylights R Compliance with CSI SectionFormat
Aug-2009 A UFGS 08 87 16 Fragment Retention Film for Glass R Compliance with CSI SectionFormat
Aug-2009 N UFGS 09 22 00 Supports for Plaster and Gypsum Board R Minor revisions
Aug-2009 N UFGS 09 29 00 Gypsum Board R Minor revisions
Aug-2009 S UFGS 09 90 00.00 40 Painting and Coating D Section merged with UFGS 09 90 00 Paints and Coatings (Preparing Activity: NAVFAC)
Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Aug-2009 A UFGS 11 13 10 Dock Levelers R Revised SD-10 Operation and Maintenance Data
Aug-2009 N UFGS 22 00 00 Plumbing, General Purpose R Subpart 1.2-Corrected lead para; 2.4.3-added Dual Flush; 2.5-added Regulatory Agencies; 2.10-modified para. & editorial corrections; 2.10.4-updated para. and subpart as, 3.9.1.1-updated para.; 3.9.5-updated para.
Aug-2009 A UFGS 23 00 00 Air Supply, Distribution, Ventilation, and Exhaust Systems R Corrections and revision throughout, plus addition of Navy tailoring
Aug-2009 N UFGS 23 05 93 Testing, Adjusting, and Balancing for HVAC R For NAVFAC projects: added notes under Project Drawings and Dalt Procedures, modified para 1.2, 3.4.1, 3.4.8, and 3.7
Aug-2009 N UFGS 23 09 23.13 20 BACnet Direct Digital Control Systems for HVAC R Within subpart 2.3.1, deleted third paragraph
Aug-2009 S UFGS 23 09 33.00 40 Electric and Electronic Control System for HVAC R Minor revisions
Aug-2009 S UFGS 23 22 25 Steam Valves R Minor revisions
Aug-2009 N UFGS 23 64 00 Packaged Water Chillers, Absorption Type R Deleted para. 2.5.5
Aug-2009 N UFGS 23 64 26 Chilled, Chilled-Hot, and Condenser Water Piping Systems R Editorial changes to subparts 2.3 & 2.4
Aug-2009 A UFGS 26 42 14.00 10 Cathodic Protection System (Sacrificial Anode) R Incorporated CCRs 1174, 1175, 1178, 1181, 1184, and 1185
Aug-2009 A UFGS 28 31 64.00 10 Fire Detection and Alarm System, Addressable R Incorporated CCRs 1499, 1500, 1501, 1502, 1503, 1504, 1505, 1506, 1507, 1509, and 1510
Aug-2009 A UFGS 31 41 16 Metal Sheet Piling R Revised sheet piling section properties
Aug-2009 N UFGS 31 62 13.20 Precast/Prestressed Concrete Piles R Major revision
Aug-2009 A UFGS 32 12 16 Hot-Mix Asphalt (HMA) for Roads R Revised JMF requirements and Tables 7 and 8 revised; changed text to active voice