Aug-2024 N UFGS Section Template (Template CCRs Only) R Within the Submittals Article, removed paragraph in the standard notes referencing the use of brackets in the standard paragraph; brackets replaced with “AIR FORCE, NAVY” and “ARMY” tailoring in the standard paragraph; outside brackets removed in the ARMY tailoring tag for the “G” submittals:
Aug-2024 N UFGS 01 14 00 Work Restrictions C 3 In response to CCR 12882, updated SPECIAL SCHEDULING REQUIREMENTS paragraph (1.4) to include list item for restricted access areas. This information was removed from UFGS-01 50 00 and relocated here.
Aug-2024 N UFGS 01 20 00 Price and Payment Procedures C 4 Updated to clarify cost loading and price and payment procedures.
Aug-2024 N UFGS 01 30 00 Administrative Requirements C 4 In response to the following CCR 15440, updated for USACE adoption of Red Zone Process; CCR 11650, added optional ARMY tailoring for submittal Color Boards and Color Board paragraph (1.3)
Aug-2024 A UFGS 01 32 01.00 10 Project Schedule C 1 Incorporated various CCRs.
Aug-2024 N UFGS 01 32 17.00 20 Cost-Loaded Network Analysis Schedules (NAS) C 1 Updated to clarify cost loading and price and payment procedures.
Aug-2024 A UFGS 01 50 00 Temporary Construction Facilities and Controls C 3 Incorporated various CCRs.
Aug-2024 N UFGS 01 91 00.15 Building Commissioning C 3 Addressed CCRs, added Commissioning Site Visits paragraph, and coordinated with updated nomenclature in UFGS-01 45 00 QUALITY CONTROL.
Aug-2024 N UFGS 03 30 00 Cast-In-Place Concrete C 9 In response to CCR 15076, added "Type IT" cements to items i, ii, and iii in paragraph Freezing and Thawing Resistance (2.5.2.2)
Aug-2024 N UFGS 05 05 20 Post-Installed Concrete and Masonry Anchors C 1 In response to CCR 15088, replaced Material Safety Data Sheets (MSDS) with Safety Data Sheets (SDS) in QUALITY ASSURANCE paragraph (1.5)
Aug-2024 N UFGS 05 50 13 Miscellaneous Metal Fabrications R Complete review and update.
Aug-2024 N UFGS 05 51 33 Metal Ladders R Complete review and update.
Aug-2024 N UFGS 06 20 00 Finish Carpentry R Complete review and update.
Aug-2024 N UFGS 07 27 19.01 Self-Adhering Air Barriers C 1 In response to CCR 13571, corrected the air leakage rate in list item b. Assembly Air Leakage, under Physical Properties paragraph (2.1.1)
Aug-2024 N UFGS 08 34 16.10 Horizontal Rolling Steel Doors C 1 In response to CCR 15267, corrected wind velocities in Wind Loads paragraph (1.3.2.1) to coordinate with UFC 3-301-01.
Aug-2024 N UFGS 08 34 16.20 Vertical Lift Fabric Doors C 2 Corrected wind velocities in Wind Loads paragraph (1.3.2.1) to coordinate with UFC 3-301-01.
Aug-2024 N UFGS 08 34 63 Detention Hollow Metal Frames, Doors, and Door Frames R Complete review and update.
Aug-2024 N UFGS 08 56 53 Blast Resistant Tempered Glass Windows C 1 In response to CCR 12317, updated section to active language (replacing "must")
Aug-2024 N UFGS 08 71 63 Detention Hardware R Complete review and update.
Aug-2024 N UFGS 09 22 00 Supports for Plaster and Gypsum Board R Complete review and update.
Aug-2024 N UFGS 09 22 36 Lath R Complete review and update.
Aug-2024 N UFGS 09 23 00 Gypsum Plastering R Complete review and update.
Aug-2024 N UFGS 09 26 00 Veneer Plaster R Complete review and update.
Aug-2024 N UFGS 09 29 00 Gypsum Board R Complete review and update. Incorporate CCRs #4960, 8088, 10091, 10122, 10479, 10609.
Aug-2024 N UFGS 09 97 23.16 Linseed Oil Protection of Concrete Surfaces R Complete review and update.
Aug-2024 N UFGS 10 21 23.16 Cubicle Track and Hardware R Complete review and update.
Aug-2024 N UFGS 10 22 13 Wire Mesh Partitions R Complete review and update. Incorporate CCRs #10216, 13813.
Aug-2024 N UFGS 10 22 26.13 Accordion Folding Partitions R Complete review and update.
Aug-2024 N UFGS 10 22 26.23 Coiling Partitions R Complete review and update.
Aug-2024 N UFGS 10 51 13 Lockers R Complete review and update including title change from “Metal Lockers” to “Lockers”
Aug-2024 N UFGS 10 56 13 Steel Shelving R Complete review and update.
Aug-2024 N UFGS 12 55 00 Detention Furniture and Accessories R Complete review and update.
Aug-2024 N UFGS 23 05 15 Common Piping for HVAC C 2 In response to CCR 13457, added requirement for Type 19 and 23 C-clamps
Aug-2024 A UFGS 23 07 00 Thermal Insulation for Mechanical Systems R Complete review and update.
Aug-2024 N UFGS 23 08 00 Commissioning of Mechanical[ and Plumbing] Systems C 1 "Quality Control (QC) Manager" to be used for all services; updated language and removed Army/Navy tailoring in CERTIFICATE OF READINESS (1.6) and PRE-FUNCTIONAL CHECKS (3.3) 
Aug-2024 N UFGS 23 09 53.00 20 Space Temperature Control Systems C 3 Added PNEUMATIC tailoring option.
Aug-2024 N UFGS 33 11 00 Water Utility Distribution Piping R Complete review and update.
Aug-2024 A UFGS 33 60 02 Aboveground Heat Distribution System R Complete review and update.
Aug-2024 A UFGS 33 61 13 Pre-Engineered Underground Heat Distribution System R Complete review and update.
Aug-2024 N UFGS 34 60 13 Electric Vehicle Charging Facility (EVCF) R Complete review and update including renumber/retitle from UFGS-11 11 37 ELECTRIC VEHICLE SUPPLY EQUIPMENT to UFGS-34 60 13 ELECTRIC VEHICLE CHARGING FACILITY (EVCF).