| Aug-2024 |
N
|
UFGS Section Template (Template CCRs Only) |
Aug-2024 |
R
|
|
Within the Submittals Article, removed paragraph in the standard notes referencing the use of brackets in the standard paragraph; brackets replaced with “AIR FORCE, NAVY” and “ARMY” tailoring in the standard paragraph; outside brackets removed in the ARMY tailoring tag for the “G” submittals: |
| Aug-2024 |
N
|
UFGS 01 14 00 Work Restrictions |
Nov-2022 |
C
|
3 |
In response to CCR 12882, updated SPECIAL SCHEDULING REQUIREMENTS paragraph (1.4) to include list item for restricted access areas. This information was removed from UFGS-01 50 00 and relocated here. |
| Aug-2024 |
N
|
UFGS 01 20 00 Price and Payment Procedures |
Nov-2020 |
C
|
4 |
Updated to clarify cost loading and price and payment procedures. |
| Aug-2024 |
N
|
UFGS 01 30 00 Administrative Requirements |
Nov-2020 |
C
|
4 |
In response to the following CCR 15440, updated for USACE adoption of Red Zone Process; CCR 11650, added optional ARMY tailoring for submittal Color Boards and Color Board paragraph (1.3) |
| Aug-2024 |
A
|
UFGS 01 32 01.00 10 Project Schedule |
Aug-2023 |
C
|
1 |
Incorporated various CCRs. |
| Aug-2024 |
N
|
UFGS 01 32 17.00 20 Cost-Loaded Network Analysis Schedules (NAS) |
Nov-2023 |
C
|
1 |
Updated to clarify cost loading and price and payment procedures. |
| Aug-2024 |
A
|
UFGS 01 50 00 Temporary Construction Facilities and Controls |
Nov-2020 |
C
|
3 |
Incorporated various CCRs. |
| Aug-2024 |
N
|
UFGS 01 91 00.15 Building Commissioning |
May-2023 |
C
|
3 |
Addressed CCRs, added Commissioning Site Visits paragraph, and coordinated with updated nomenclature in UFGS-01 45 00 QUALITY CONTROL. |
| Aug-2024 |
N
|
UFGS 03 30 00 Cast-In-Place Concrete |
Feb-2019 |
C
|
9 |
In response to CCR 15076, added "Type IT" cements to items i, ii, and iii in paragraph Freezing and Thawing Resistance (2.5.2.2) |
| Aug-2024 |
N
|
UFGS 05 05 20 Post-Installed Concrete and Masonry Anchors |
May-2022 |
C
|
1 |
In response to CCR 15088, replaced Material Safety Data Sheets (MSDS) with Safety Data Sheets (SDS) in QUALITY ASSURANCE paragraph (1.5) |
| Aug-2024 |
N
|
UFGS 05 50 13 Miscellaneous Metal Fabrications |
Aug-2024 |
R
|
|
Complete review and update. |
| Aug-2024 |
N
|
UFGS 05 51 33 Metal Ladders |
Aug-2024 |
R
|
|
Complete review and update. |
| Aug-2024 |
N
|
UFGS 06 20 00 Finish Carpentry |
Aug-2024 |
R
|
|
Complete review and update. |
| Aug-2024 |
N
|
UFGS 07 27 19.01 Self-Adhering Air Barriers |
Aug-2023 |
C
|
1 |
In response to CCR 13571, corrected the air leakage rate in list item b. Assembly Air Leakage, under Physical Properties paragraph (2.1.1) |
| Aug-2024 |
N
|
UFGS 08 34 16.10 Horizontal Rolling Steel Doors |
Nov-2021 |
C
|
1 |
In response to CCR 15267, corrected wind velocities in Wind Loads paragraph (1.3.2.1) to coordinate with UFC 3-301-01. |
| Aug-2024 |
N
|
UFGS 08 34 16.20 Vertical Lift Fabric Doors |
Aug-2021 |
C
|
2 |
Corrected wind velocities in Wind Loads paragraph (1.3.2.1) to coordinate with UFC 3-301-01. |
| Aug-2024 |
N
|
UFGS 08 34 63 Detention Hollow Metal Frames, Doors, and Door Frames |
Aug-2024 |
R
|
|
Complete review and update. |
| Aug-2024 |
N
|
UFGS 08 56 53 Blast Resistant Tempered Glass Windows |
Aug-2020 |
C
|
1 |
In response to CCR 12317, updated section to active language (replacing "must") |
| Aug-2024 |
N
|
UFGS 08 71 63 Detention Hardware |
Aug-2024 |
R
|
|
Complete review and update. |
| Aug-2024 |
N
|
UFGS 09 22 00 Supports for Plaster and Gypsum Board |
Aug-2024 |
R
|
|
Complete review and update. |
| Aug-2024 |
N
|
UFGS 09 22 36 Lath |
Aug-2024 |
R
|
|
Complete review and update. |
| Aug-2024 |
N
|
UFGS 09 23 00 Gypsum Plastering |
Aug-2024 |
R
|
|
Complete review and update. |
| Aug-2024 |
N
|
UFGS 09 26 00 Veneer Plaster |
Aug-2024 |
R
|
|
Complete review and update. |
| Aug-2024 |
N
|
UFGS 09 29 00 Gypsum Board |
Aug-2024 |
R
|
|
Complete review and update. Incorporate CCRs #4960, 8088, 10091, 10122, 10479, 10609. |
| Aug-2024 |
N
|
UFGS 09 97 23.16 Linseed Oil Protection of Concrete Surfaces |
Aug-2024 |
R
|
|
Complete review and update. |
| Aug-2024 |
N
|
UFGS 10 21 23.16 Cubicle Track and Hardware |
Aug-2024 |
R
|
|
Complete review and update. |
| Aug-2024 |
N
|
UFGS 10 22 13 Wire Mesh Partitions |
Aug-2024 |
R
|
|
Complete review and update. Incorporate CCRs #10216, 13813. |
| Aug-2024 |
N
|
UFGS 10 22 26.13 Accordion Folding Partitions |
Aug-2024 |
R
|
|
Complete review and update. |
| Aug-2024 |
N
|
UFGS 10 22 26.23 Coiling Partitions |
Aug-2024 |
R
|
|
Complete review and update. |
| Aug-2024 |
N
|
UFGS 10 51 13 Lockers |
Aug-2024 |
R
|
|
Complete review and update including title change from “Metal Lockers” to “Lockers” |
| Aug-2024 |
N
|
UFGS 10 56 13 Steel Shelving |
Aug-2024 |
R
|
|
Complete review and update. |
| Aug-2024 |
N
|
UFGS 12 55 00 Detention Furniture and Accessories |
Aug-2024 |
R
|
|
Complete review and update. |
| Aug-2024 |
N
|
UFGS 23 05 15 Common Piping for HVAC |
May-2022 |
C
|
2 |
In response to CCR 13457, added requirement for Type 19 and 23 C-clamps |
| Aug-2024 |
A
|
UFGS 23 07 00 Thermal Insulation for Mechanical Systems |
Aug-2024 |
R
|
|
Complete review and update. |
| Aug-2024 |
N
|
UFGS 23 08 00 Commissioning of Mechanical[ and Plumbing] Systems |
May-2023 |
C
|
1 |
"Quality Control (QC) Manager" to be used for all services; updated language and removed Army/Navy tailoring in CERTIFICATE OF READINESS (1.6) and PRE-FUNCTIONAL CHECKS (3.3) |
| Aug-2024 |
N
|
UFGS 23 09 53.00 20 Space Temperature Control Systems |
Feb-2010 |
C
|
3 |
Added PNEUMATIC tailoring option. |
| Aug-2024 |
N
|
UFGS 33 11 00 Water Utility Distribution Piping |
Aug-2024 |
R
|
|
Complete review and update. |
| Aug-2024 |
A
|
UFGS 33 60 02 Aboveground Heat Distribution System |
Aug-2024 |
R
|
|
Complete review and update. |
| Aug-2024 |
A
|
UFGS 33 61 13 Pre-Engineered Underground Heat Distribution System |
Aug-2024 |
R
|
|
Complete review and update. |
| Aug-2024 |
N
|
UFGS 34 60 13 Electric Vehicle Charging Facility (EVCF) |
Aug-2024 |
R
|
|
Complete review and update including renumber/retitle from UFGS-11 11 37 ELECTRIC VEHICLE SUPPLY EQUIPMENT to UFGS-34 60 13 ELECTRIC VEHICLE CHARGING FACILITY (EVCF). |