View/Download
PDF   ZIP  
Publish Date
Pages
57
Spec. Division
41 - Material Processing and Handling Equipment
CCR

History: Below is a listing of the Revisions and Changes made to this UFGS.

KEYPREPARING ACTIVITY (PA)A ArmyN NavyF Air ForceS NASA [ARCHIVED]
ACTIONN NewR RevisionC ChangeD Deletion
Release PA Action Change # Nature of Change or Revision
Feb-2023 N C 3 Added an option for alternate wire rope in Division 2 hazardous areas. Updated formatting, foreign standard practices, and provided clarifications.
Nov-2022 N C 2 Updated formatting with some changes to technical requirements.
May-2022 N C 1 Added technical requirement to second text paragraph in subpart 2.3.2.2 Load Block and Hook
Feb-2022 N R Complete review and update. Clarified terminology and made changes to submittals along with technical and testing requirements.
Nov-2020 N N New crane section developed specifically for aircraft hangars.