Publish Date
              Pages
              16
          Spec. Division
              01 - General Requirements
          CCR
              
          History: Below is a listing of the Revisions and Changes made to this UFGS.
| KEY | PREPARING ACTIVITY (PA) | A Army | N Navy | F Air Force | S NASA [ARCHIVED] | 
|---|---|---|---|---|---|
| ACTION | N New | R Revision | C Change | D Deletion | 
| Release | PA | Date | Action | Change # | Nature of Change or Revision | 
|---|---|---|---|---|---|
| Feb-2025 | N | Nov-2020 | C | 5 | In response to CCR 15538, update made to paragraph Obligation of Government Payments (1.7.1).  | 
              
| Aug-2024 | N | Nov-2020 | C | 4 | Updated to clarify cost loading and price and payment procedures. | 
| Feb-2023 | N | Nov-2020 | C | 3 | In response to CCR 12177, replaced "lump sum" with "Job" in second Note for Army projects, removed "lump sum" from DREDGING paragraph (1.11). | 
| Aug-2021 | N | Nov-2020 | C | 2 | In response to CCR 9972, included timeline requirements for both Schedule of Prices and Earned Value Report and corrected typo in Note in Data Required paragraph. | 
| Feb-2021 | N | Nov-2020 | C | 1 | In response to CCR 9618, reference to FAR 32.503-6 has been replaced with "FAR 32.103 Progress payments under construction contracts" in paragraph (1.7.1) "Obligation of Government Payments" . | 
| Nov-2020 | N | Nov-2020 | N | New Unified Section; Superseding UFGS 01 20 00.00 20 and UFGS 01 22 00.00 10 PRICE AND PAYMENT PROCEDURES |