Release PA Action Change # Nature of Change or Revision
Feb-2024 N C 7 In response to CCRs 9060, 13651, and 14220, ‘Pump Discharge Valve’ (submittal and paragraph) has been removed from the section as it conflicted with UFC 3-410-01 Heating, Ventilating, and Air Conditioning Systems’.
Nov-2022 N C 6 Updated paragraph "Valves" (3.1.5) removed sentence regarding omitting isolation valves
Nov-2019 N C 5 Incorporated dispersal of criteria from the retired UFC 3-440-05N TROPICAL ENGINEERING, and the addition of corrosion protection criteria to coordinate with UFC 1-200-01 DoD BUILDING CODE.
Feb-2017 N C 4 Updated Technical Note in 2.2.2-Fittings and End Connections (Joints)
Aug-2015 N C 3 UFGS sustainability/energy updates to comply with Navy and DoD policies to enforce requirements of UFC 1-200-02 "High Performance and Sustainable Building Requirements".
May-2015 N C 2 Modified subparts 2.2.2, 2.2.2.4, 2.6.3, and 3.1.4.4 to show grooved connections are not used on NAVFAC projects.
Nov-2013 N C 1 Added subparts 2.3 and 3.2; revised subparts 2.2.2.2, 2.4.1, 2.7.13. 2.7.16, 2.8.5, 2.17.5.1 and 3.5.2
Aug-2009 N R Editorial changes to subparts 2.3 & 2.4
Apr-2008 N R Section References (SRF) update paragraph 2.12
Jan-2007 N R Added note "Not for use in Navy projects" to paragraphs 'Piping for Steam and Condensate' (2.3) and 'Piping for High-Pressure Compressed-Air Systems' (2.4)