Overview

Automated Data Processing Center for PC System (ADP PC) space types is a facility for "horizontal" data processing systems including floor- and counter-mounted units with non-critical uptime requirements. ADP PC space types include facilities for RISC and Pentium-based servers contained in individual equipment towers.

Space Attributes

Because of the computer and electronic equipment housed within the ADP PC, the spaces require regulated temperature and humidity (usually accomplish by zoned systems), and reliable power 24 hours per day. Typical features of ADP PC space types include the list of applicable design objectives elements as outlined below. For a complete list and definitions of the design objectives within the context of whole building design, click on the titles below.

Functional / Operational

  • Occupancy: Occupancy Classification for ADP PC is Business Occupancy B2, with sprinkler protected construction and GSA Acoustical Class B2 for spaces with concentrations of noisy equipment.
  • Raised floors: Raised floors are the preferred system for distribution of critical services (power, voice, data, and HVAC) in ADP PC space types. Raised floors for ADP PC may have low-pressure high induction diffusers and be constructed of concrete filled metal pans at 24" modules with pedestal and stringer support, with intermediate support.
  • Dual path service lines for power: Dual path service lines ensure a constant power supply, which is critical to the operations of ADP PC with concentrations of noisy equipment.
  • Redundant cooling unit: ADP PC space types are usually equipped with redundant cooling capacity to maintain the low temperature required by the computer equipment. This could consist of a split air-cooled, air-conditioning unit with 24-hour operation and setback thermostats. Acoustical transfer ducts should be installed at all acoustically rated partitions for noise control. For more information, see WBDG High-Performance HVAC.

Productive

  • Acoustic control: Sound baffles are provided at all acoustically rated partitions for the air supply system to control noise.
  • Uninterruptible Power Supply (UPS): Emergency power and uninterruptible power supply (UPS) are provided to meet all electrical requirements of the entire ADP PC (server) facility for at least 30 minutes. For more information, see WBDG Productive—Assure Reliable Systems and Spaces.

Secure / Safe

Example Program

The following is a representative building program.

ADP PC

Description
Tenant Occupiable Areas
Qty. SF Each Space Req'd. Sum Actual SF Tenant Usable Factor Tenant USF
Facilities       936    
    Supervisor Office 1 100 100      
    Support Technician Workstation 2 80 160      
    Reference Library 4 12 48      
    Magnetic Media Storage 4 12 48      
    Server Racks/Towers 24 8 192      
    Multiplexor/Controller Racks 2 22 44      
    Printer 2 22 44      
    HVAC Unit 1 60 60      
    Supplies and Parts Storage 1 120 120      
    LAN Switches/
    Telephone Switches
1 60 60      
    Electrical Room 1 60 60      
             
    Tenant Suite     936 936 1.31 1,227
Tenant Usable Areas           1,227

Example Plans

The following is representative of typical tenant plans.

ADP PC Intensive Space Type

Example Construction Criteria

For GSA, the unit costs for ADP PC space types are based on the construction quality and design features in the following table (PDF 66 KB, 5 pgs). This information is based on GSA's benchmark interpretation and could be different for other owners.

Relevant Codes and Standards

The following agencies and organizations have developed codes and standards affecting the design of ADP PC spaces. Note that the codes and standards are minimum requirements. Architects, engineers, and consultants should consider exceeding the applicable requirements whenever possible:

Major Resources

WBDG

Building Types

Educational Facilities, Federal Courthouse, Health Care Facilities, Land Port of Entry, Libraries, Office Building, Research Facilities, Warehouse

Design Objective

Functional / Operational—Ensure Appropriate Products / Systems Integration, Productive—Assure Reliable Systems and Spaces, Secure / Safe—Provide Security for Building Occupants and Assets

Project Management

Building Commissioning

Publications