UFGS Changes and Revisions  Subscribe to UFGS Changes and Revisions

Related Materials: Policy on UFGS Changes and Revisions

Below is a listing of the Revisions and Changes made to UFGS Sections for each quarterly release.

To view a list for a specific UFGS Release, select the UFGS release date from the 'Release' drop-down and click 'Apply'.

To view a list of all the revisions and changes made to a specific UFGS Section, select 'Any' from the "Release' drop down, type the Section number into the Search bar and select the Section to view, then click 'Apply'.

After clicking 'Apply', you can PRINT REPORT, which will include the nature of the change/revision.

To view the complete detailed history of all the revisions and changes made to a UFGS Section, click on the Section title.

KEY PREPARING ACTIVITY (PA) A Army N Navy F Air Force S NASA
ACTION N New R Revision C Change D Deletion
Release PA UFGS Section Action Change # Nature of Change or Revision
Nov-2022 A UFGS 32 13 14.13 Concrete Paving for Airfields and Other Heavy Duty Pavements R Complete review and update
Nov-2022 A UFGS 32 13 15.20 Concrete Pavement for Fuel Storage Containment Dikes R Complete review and update to include section title change from CONCRETE PAVEMENT FOR CONTAINMENT DIKES to CONCRETE PAVEMENT FOR FUEL STORAGE CONTAINMENT DIKES
Nov-2022 F UFGS 32 31 13 Chain Link Fences and Gates C Administrative Change: Preparing Activity changed from NASA to Air Force.
Nov-2022 F UFGS 33 05 23.13 Utility Horizontal Directional Drilling C Administrative Change: Preparing Activity changed from NASA to Air Force.
Nov-2022 F UFGS 33 51 39 Monitoring Wells C Administrative Change: Preparing Activity changed from NASA to Air Force.
Nov-2022 A UFGS 33 56 19 Fuel Impermeable Liner System R Complete review and update
Nov-2022 N UFGS 33 56 21.17 Single Wall Aboveground Fixed Roof Steel POL Storage Tank C 2 In response to various CCRs, including #11869, added ASME BPVC IX to "References" and "Welding Qualifications" paragraph (1.6.1); #11875 added API Std 650 to "Shell Height" paragraph (1.5.1.2), #11983 updated "Roof Perimeter Guardrail" paragraph (2.13.10) and added new Designer Note; #6124 removed wiper requirement and added non-corrosive materials for tape drum and cassette to "Mechanical Tape Level Gauge" (2.13.5) and (2.13.6) paragraphs; and #11261, revised opening Note to coordinate use of floating pans with UFC 3-460-01.
Nov-2022 A UFGS 35 45 01 Vertical Pumps, Axial-Flow and Mixed-Flow Impeller-Type C 2 Vibration standards have been updated in the document and pump baseplate design updated to follow API standards
Nov-2022 N UFGS 41 22 13.15 Bridge Cranes, Overhead Electric, Under Running Trolley R Complete review and major update, including title change (from BRIDGE CRANES, OVERHEAD ELECTRIC, UNDER RUNNING). Clarified terminology and made changes to submittals along with changes to technical and testing requirements.
Nov-2022 N UFGS 41 22 13.55 Bridge Cranes, Under Running, Aircraft Hangar C 2 Updated formatting with some changes to technical requirements.
Nov-2022 A UFGS 44 10 00 Air Pollution Control R Complete review and update
Aug-2022 A UFGS 01 35 29.13 Health, Safety, and Emergency Response Procedures for Contaminated Sites C 1 Incorporated CCR 8953.
Aug-2022 A UFGS 01 50 00 Temporary Construction Facilities and Controls C 2 Incorporated CCRs 10035, 10883, and 10885.
Aug-2022 N UFGS 01 57 19 Temporary Environmental Controls R Revised to align with current industry standards and DoD requirements. This Section supersedes UFGS-01 57 19.00 20 Supplemental Temporary Environmental Controls as all requirements are contained within this Tri-Service, tailorable specification as reorganized paragraphs in a hierarchical presentation.
Aug-2022 N UFGS 01 57 19.01 20 Supplemental Temporary Environmental Controls D Superseded by UFGS 01 5719 Temporary Environmental Controls Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Aug-2022 N UFGS 01 58 00 Project Identification C 5 In response to CCR 11903, corrected placement of tailoring tags and updated specifier notes throughout.
Aug-2022 A UFGS 02 41 00 [Demolition] [and] [Deconstruction] R Complete review and update.
Aug-2022 A UFGS 03 11 19.00 Insulating Concrete Forming R Section has been "Reinstated without Revision" as UFGS-03 11 19.00 Insulating Concrete Forming (new section number only) [was archived in 2019,]
Aug-2022 N UFGS 03 30 00 Cast-In-Place Concrete C 4 In response to the following CCRs: 10852, deleted paragraph Maximum Allowable Construction Joint Spacing (3.11.1) and list items a. and b.; 11572, updated Concrete Mix Design paragraph (1.6.1.2); 11445, updated Table under Sulfate Resistance paragraph (2.5.2.4 list item a.); 11120, removed list item b. under Reinforcement paragraph (6.2) and added list item e. under Epoxy-Coated Reinforcing Bars paragraph (2.6.1.2); and 11115, added ASTM A1094/A1094M to the Reference Article and as an option in paragraph Galvanized Reinforcing Bars (2.6.1.1) list item a.
Aug-2022 A UFGS 09 06 00 Schedules for Finishes R Complete review and update.
Aug-2022 N UFGS 09 97 13.27 High Performance Coating for Steel Structures C 1 The May 2022 version of this Section has been made inactivate as it conflicted with FAR requirements; the February 2021 version has been reinstated with changes made to TEST KITS (subparts 2.6.1 and 2.6.2)
Aug-2022 S UFGS 12 31 00 Manufactured Metal Casework D Archived - Casework is specified under Div 6 Wood and plastic. Casework is under the general contract, and is not under furnishings. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Aug-2022 S UFGS 12 32 00 Manufactured Wood Casework D Archived - Casework is specified under Div 6 Wood and plastic. Casework is under the general contract, and is not under furnishings. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Aug-2022 S UFGS 12 34 00 Manufactured Plastic Casework D Archived - Casework is specified under Div 6 Wood and plastic. Casework is under the general contract, and is not under furnishings. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Aug-2022 S UFGS 12 36 00 Countertops D Archived - Casework is specified under Div 6 Wood and plastic. Casework is under the general contract, and is not under furnishings. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Aug-2022 S UFGS 22 05 83.63 Cured-In-Place Pipe (CIPP) Lining for Plumbing Applications R Update technical requirements, references and format. Incorporated CCR# 5917, 7843
Aug-2022 S UFGS 23 31 13.00 40 Metal Ducts R Update technical requirements, references and format. Incorporated CCR# 10513
Aug-2022 S UFGS 23 36 00.00 40 Air Terminal Units R Update technical requirements, references and format. Incorporated CCR# 4530, 6338, 6340, 9585
Aug-2022 S UFGS 23 37 13.00 40 Diffusers, Registers, and Grills R Update technical requirements, references and format. Incorporated CCR# 4530, 6338, 6340, 9585
Aug-2022 A UFGS 23 63 00.00 10 Cold Storage Refrigeration Systems D Superseded by unified UFGS 23 63 00.00 COLD STORAGE REFRIGERATION SYSTEMS. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Aug-2022 A UFGS 23 63 00.00 Cold Storage Refrigeration Systems N Superseding UFGS 23 63 00.00 10 COLD STORAGE REFRIGERATION SYSTEMS.
Aug-2022 S UFGS 23 82 16.00 40 Air Coils R Update technical requirements, references and format.
Aug-2022 A UFGS 26 28 00.00 10 Motor Control Centers, Switchboards and Panelboards R Complete review and update.
Aug-2022 N UFGS 31 31 16.13 Chemical Termite Control R Complete review and update.
Aug-2022 N UFGS 31 31 16.19 Termite Control Barriers R Complete review and update.
Aug-2022 A UFGS 32 11 23.23 Base Course Drainage Layers R Complete review and update
Aug-2022 N UFGS 33 52 80 Liquid Fuels Pipeline Coating Systems R Complete review and update.
Aug-2022 A UFGS 35 01 41.00 10 Electromechanical Operating Machinery for Locks and Dams C 2 Incorporated various CCRs.
Aug-2022 A UFGS 35 20 14 Stoplogs R Complete review and update.
Aug-2022 A UFGS 35 20 16.33 Hydraulic Miter Gates R Complete review and update including section title change from MITER GATES to HYDRAULIC MITER GATES.
Aug-2022 A UFGS 35 20 16.39 Hydraulic Sector Gates R Complete review and update including section title change from SECTOR GATES to HYDRAULIC SECTOR GATES.
Aug-2022 A UFGS 35 20 16.46 Hydraulic Tainter Gates and Anchorages R Complete review and update including section title change from TAINTER GATES AND ANCHORAGES to HYDRAULIC TAINTER GATES AND ANCHORAGES.
Aug-2022 A UFGS 35 20 16.53 Hydraulic Vertical Lift Gates R Complete review and update including section title change from VERTICAL LIFT GATES to HYDRAULIC VERTICAL LIFT GATES.
Aug-2022 A UFGS 35 20 16.59 Closure Gates R Complete review and update including section title change from CLOSURE GATES to HYDRAULIC CLOSURE GATES.
Aug-2022 A UFGS 35 45 01 Vertical Pumps, Axial-Flow and Mixed-Flow Impeller-Type C 1 Incorporated various CCRs.
Aug-2022 N UFGS 46 07 53 Packaged Wastewater Treatment Equipment C 1 In response to CCR 11920, NASA tailoring was added to the Electrical Work paragraph (3.2.2)
May-2022 N UFGS 00 22 13.00 20 Supplementary Instructions to Offerors D This Section has been removed from the UFGS data set and superseded by a Word document (for NAVFAC use). The new Price Schedule can be accessed here. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
May-2022 N UFGS 01 30 00 Administrative Requirements C 2 Per CCR 9893, updated the Note in paragraph COLOR BOARDS FOR AIR FORCE PROJECTS (1.3) tailored for AIR FORCE to include AFI citation.
May-2022 A UFGS 01 31 20 Project Technical Data Management and Visualization N New UFGS
May-2022 N UFGS 01 58 00 Project Identification C 4 Per CCR 11078, updated Construction Project Signs paragraph (1.4.3) tailored for ARMY and AIR FORCE to address project identification signs for Air Force projects managed by USACE.
May-2022 A UFGS 01 91 00.15 10 Total Building Commissioning C 3 Updated qualifications for electrical technical commissioning specialist in response to CCRs 9054, 9096, 9741, 9970, 10182, and 10471. Updated burn-in duration for lamps in response to CCR 9218. Updated paragraph "Design Review" in response to CCRs 9220, 9222, and 9237. Updated and changed paragraph "Acceptance" to "Equipment and Systems Deficiencies Check" in response to CCR 9223.
May-2022 N UFGS 02 85 00 Mold Remediation C 1 Per CCR 11701, removed reference to UFGS 00 22 13.00 20 in first Editor’s Note of Description of Work paragraph (1.3.1)
May-2022 N UFGS 05 05 20 Post-Installed Concrete and Masonry Anchors N Unified / Section Number Change: Superseding 05 05 20.00 27 without Revision
May-2022 N UFGS 05 05 20.00 27 Post-Installed Concrete and Masonry Anchors D Section Number Change: Superseded by UFGS-05 05 20 without Revision. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
May-2022 N UFGS 09 97 13.17 Three Coat Epoxy Interior Coating of Welded Steel Petroleum Fuel Tanks R Complete review and update.
May-2022 N UFGS 09 97 13.27 High Performance Coating for Steel Structures R 08/25/2022: this version has been made inactive and replaced with the previous Feb 2021 version. Complete review and update.
May-2022 A UFGS 13 48 73 Seismic Control For Miscellaneous Equipment R Superseding UFGS 13 48 73 SEISMIC CONTROL FOR MECHANICAL EQUIPMENT without revision in response to CCR 11530. Nontechnical section title change.
May-2022 S UFGS 22 15 09.00 40 General Service Compressed-Air Systems Cleaning Procedures R Revision: Update technical requirements, references and format.
May-2022 S UFGS 23 01 30.41 HVAC System Cleaning R Revision: Update technical requirements, references and format.
May-2022 S UFGS 23 05 15 Common Piping for HVAC R Revision: Update technical requirements, references format, and incorporate the following CCRs: 7186, 7266, 7343, 8631, 8858, 9386, 9765, 10198, 10295, 10931, 11252, 11341, 11342, 11343, 11344, 11486
May-2022 S UFGS 23 05 48.00 40 Vibration and Seismic Controls for HVAC Piping and Equipment R Revision: Update technical requirements, references format, and incorporate the following CCRs: 6858, 7126
May-2022 N UFGS 26 13 00 SF6/High-Firepoint Fluids Insulated Pad-Mounted Switchgear C 1 Per CCR 8883, updated Automatic Switch Controls paragraph (2.1.4) with options for 120Vac control power.
May-2022 A UFGS 27 51 16 Public Address Systems C 1 Incorporated CCR 4973
May-2022 N UFGS 31 62 13.13 Cast-In-Place Concrete Piles C 2 Per CCR 11703, removed reference to UFGS 00 22 13.00 20 in Measurement and Payment paragraph (1.2.2)
May-2022 N UFGS 31 62 13.20 Precast/Prestressed Concrete Piles C 1 Per CCR 11704, removed reference to UFGS 00 22 13.00 20 in UNIT PRICE paragraph (1.6)
May-2022 N UFGS 31 62 13.24 Concrete Cylinder Piles C 1 Per CCR 11705, removed reference to UFGS 00 22 13.00 20 in UNIT PRICE paragraph (1.6)
May-2022 N UFGS 31 62 13.26 Pressure-Injected Footings C 1 Per CCR 11707, removed reference to UFGS 00 22 13.00 20 in Unit Price paragraph (1.4.3)
May-2022 N UFGS 31 62 16.13 Steel Pipe Piles C 1 Removed reference to UFGS 00 22 13.00 20 in Unit Price paragraph (1.4.4)
May-2022 N UFGS 31 62 16.16 Steel H-Piles C 1 Per CCR 11708, removed reference to UFGS 00 22 13.00 20 in Unit Price paragraph (1.4.3)
May-2022 N UFGS 31 62 19 Timber Piles C 1 Per CCR 11709, removed reference to UFGS 00 22 13.00 20 in Unit Price paragraph (1.4.3)
May-2022 N UFGS 31 62 19.13 Timber Marine Piles C 2 Per CCR 11710, removed reference to UFGS 00 22 13.00 20 in BASIS OF BIDS paragraph (1.5)
May-2022 N UFGS 31 62 50 Densified Aggregate Piers C 1 Per CCR 11712, removed reference to UFGS 00 22 13.00 20 in Unit Price paragraph (1.4.3)
May-2022 N UFGS 31 63 26.60 [Grouted] Helical Piles C 1 Per CCR 11716, removed reference to UFGS 00 22 13.00 20 in Unit Price paragraph (1.4.3)
May-2022 A UFGS 32 01 17.61 Sealing Cracks in Asphalt Paving R Complete review and update.
May-2022 A UFGS 32 11 20 [Base Course for Rigid][ and ][Subbase] [Select-Material] [For Flexible Paving] R Complete review and update, including section title change from [BASE COURSE FOR RIGID][ AND ][SUBBASES FOR FLEXIBLE] PAVING to [BASE COURSE FOR RIGID][ AND ][SUBBASE] [SELECT-MATERIAL] [FOR FLEXIBLE PAVING].
May-2022 A UFGS 32 11 23 [Aggregate Base Course] [and][or] [Graded Crushed Aggregate Base Course] for Flexible Paving R Complete review and update, including section title change from AGGREGATE BASE COURSE to [AGGREGATE BASE COURSE] [AND/OR][GRADED CRUSHED AGGREGATE BASE COURSE] FOR FLEXIBLE PAVING.
May-2022 A UFGS 32 12 15.13 Asphalt Paving for Airfields C 1 In response to CCR 10561, added appropriate references for Navy and NASA associated with paragraphs CONTRACTOR QUALITY CONTROL STAFF, CONTRACTOR QUALITY CONTROL and GENERAL QUALITY CONTROL REQUIREMENTS. In response to CCR 11001 and CCR 9916, consolidated and clarified straightedge testing for longitudinal and transverse smoothness as well as revised Profilograph Testing requirements and associated acceptance Table 2. Prohibited the use of recycled asphalt shingles (RAS) in the asphalt mixture.
May-2022 A UFGS 33 51 43 Instrumentation and Performance Monitoring of Structures N New UFGS
May-2022 A UFGS 35 20 20 Electrical Equipment for Gate Hoist R Complete review and update.
May-2022 A UFGS 35 45 03.00 10 Speed Reducers for Storm Water Pumps R Complete review and update.
May-2022 N UFGS 41 22 13.55 Bridge Cranes, Under Running, Aircraft Hangar C 1 Added technical requirement to second text paragraph in subpart 2.3.2.2 Load Block and Hook
Feb-2022 N UFGS 01 14 00 Work Restrictions C 14 In response to CCR 11282, "Naval Base, Norfolk VA" and "Naval Air Station, Norfolk, VA" changed to "Naval Station Norfolk, Norfolk, VA".
Feb-2022 N UFGS 01 35 13 Special Project Procedures C 1 In response to CCR 9539, specifier notes were added to the Definitions and Airfield Obstruction Lights paragraphs; tailoring was corrected to NAVFAC HI for paragraphs 3.2.3 "RIMPAC", 3.2.4 "December 7, 1941", and 3.2.5 "Pearl Harbor"
Feb-2022 N UFGS 01 35 26 Governmental Safety Requirements C 3 Added "Government Designated Authority (GDA)" to Dive Safety Requirements paragraph. In response to CCR 11124, updated first sentence in Competent Person, Cranes and Rigging paragraph.
Feb-2022 N UFGS 01 58 00 Project Identification C In reference to CCR 11189, Project Sign Details (PDF and zip files) found under Related Materials have been updated. Classified as a clerical change.
Feb-2022 N UFGS 08 32 13 Aluminum Sliding Glass Doors C 1 In response to CCR 10477, bracket placement corrected to surround EXTRA STOCK paragraph (1.5)
Feb-2022 S UFGS 08 33 23 Overhead Coiling Doors C 1 CCR10484: Adjusted tailoring option to entire portion of subpart 2.2.5 ELECTRIC DOOR OPERATORS
Feb-2022 N UFGS 08 51 23 Steel Windows C 1 In response to CCR 10430, corrected specifier note for electrical CSI division, provided Army tailoring option for specific submittals within Submittal Article (1.2), and removed brackets from Thermal Performance paragraph (1.5.2)
Feb-2022 N UFGS 08 52 00 Wood Windows C 1 In response to the following CCRs: 10475, 11217, and 11224, submittal item "Engineered Wood Products" has been tailored for NAVY in Submittal Article and corrected submittal tag with in the section text to the proper paragraph Engineered Wood Products (1.2.3). CCRs 10475 and 11225, removed brackets and NAVY tailoring for submittal item "Adhesives" to correct discrepancy since the Adhesives submittal paragraph (2.3.1) is not tailored.
Feb-2022 N UFGS 08 53 00 Plastic Windows C 1 In response to CCR 10476, adjusted location of NAVY tailoring in Material Identification paragraph.
Feb-2022 N UFGS 08 56 46.10 20 Radio Frequency Shielded Enclosures, Demountable Type C 1 In response to CCR 10407, corrected CSI division for Electrical in specifier note for Grounding paragraph (3.8)
Feb-2022 N UFGS 08 56 46.20 20 Radio Frequency Shielded Enclosures, Welded Type C 2 In response to CCR 10408, corrected CSI division for Electrical in specifier note for Grounding paragraph (3.7)
Feb-2022 N UFGS 08 71 00 Door Hardware C 4 In response to the following: CCR 9281, the Hardware Schedule Table (1.5) has been replaced with a hardware item list and a hardware schedule list; CCR 10303, deleted Texture paragraph (2.3.12.3) as it does not apply.
Feb-2022 A UFGS 23 30 00 HVAC Air Distribution C 1 Incorporated CCR 2491.
Feb-2022 N UFGS 23 52 33.01 20 Steam Heating Plant Watertube (Shop Assembled) Coal/Oil or Coal C 3 Under Related Requirements, "VAMS 23 09 53.00 20 CONTROLS AND INSTRUMENTATION BOILER PLANT" replaced with "UFC 3-430-11 BOILER PLANT INSTRUMENTATION AND CONTROL SYSTEMS"; also, the term "VAMS" has been removed throughout this section.
Feb-2022 N UFGS 23 52 33.02 20 Steam Heating Plant Watertube (Field Erected) Coal/Oil or Coal C 5 The term "VAMS" has been removed throughout this section.
Feb-2022 N UFGS 23 52 33.03 20 Water-Tube Boilers, Oil/Gas or Oil C 4 The term "VAMS" has been removed throughout this section.
Feb-2022 N UFGS 26 05 33 Dockside Power Connection Stations R Complete review; revised to incorporate CCRs.
Feb-2022 N UFGS 33 11 00 Water Utility Distribution Piping C 1 Changes made to incorporate multiple CCRs, including updating lead free and PE Pipe requirements and adding PE tubing.
Feb-2022 A UFGS 34 71 13.19 Crash Rated Active Vehicle Barriers and Controls D Superseded by UFGS 34 75 13.13 CRASH RATED ACTIVE VEHICLE BARRIERS AND CONTROLS. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.